Bidder Selection Plan

Second contractor selection plan for project: Construction of flooded road from Quang Luu commune center to Quang Thach commune center connecting provincial road 22

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 14:45 06/01/2026
Contractor Selection Plan ID
PL2600001710-00
Publishing time
14:43 06/01/2026
Posting Status
Published
Contractor selection plan name
Second contractor selection plan for project: Construction of flooded road from Quang Luu commune center to Quang Thach commune center connecting provincial road 22
Investment objective
Building a flooded road from the center of Quang Luu commune to the center of Quang Thach commune connecting provincial road 22 to form a smooth traffic network between the centers of two communes Quang Luu and Quang Thach (old) with provincial road 22 to meet the travel needs of people, serve rescue work, create favorable conditions for trade and exchange of goods and services, contributing to promoting socio-economic development of Trung Thuan commune in general and other communes. the Northwest, Quang Tri province in particular.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2600000383-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
Ban Quản lý dự án ODA Quảng Trạch
Approval date
05/01/2026
Approval ID
02/QĐ-DA
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 8
1.Tender package No 5: Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
3 years
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Monitoring the construction process
Capital source details
1] Medium-term public investment capital Provincial budget for the period 2021-2025: 1,000 million VND and for the period 2026-2030: 24,000 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Tender package No 6: Construction quality inspection
Tender/ Prequalification Notice ID
Contract execution period
3 years
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Inspect the quality of all project items according to regulations
Capital source details
[1] Medium-term public investment capital Provincial budget for the period 2021-2025: 1,000 million VND and for the period 2026-2030: 24,000 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.Tender package No 7: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
3 years
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Perform the remedy when the project has a problem
Capital source details
Medium-term public investment capital Provincial budget for the period 2021-2025: 1,000 million VND and for the period 2026-2030: 24,000 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Tender package No 8: Construction and installation (Including contingency costs and traffic assurance costs)
Tender/ Prequalification Notice ID
Contract execution period
900 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Execute construction and ensure traffic safety of the project according to the approved design
Capital source details
Medium-term public investment capital Provincial budget for the period 2021-2025: 1,000 million VND and for the period 2026-2030: 24,000 million VND.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Bidding package No. 9: Prepare bidding documents, request documents + evaluate bid documents, proposal documents
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents and evaluate bids for construction and installation packages
Capital source details
Medium-term public investment capital Provincial budget for the period 2021-2025: 1,000 million VND and for the period 2026-2030: 24,000 million VND.
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
6.Bidding package No. 10: Appraisal of bidding documents, request documents + Appraisal of contractor selection results
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of bidding documents and the results of the contractor selection of construction and installation package
Capital source details
Medium-term public investment capital Provincial budget for the period 2021-2025: 1,000 million VND and for the period 2026-2030: 24,000 million VND.
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
7.Package 11: Project management
Tender/ Prequalification Notice ID
Contract execution period
3 years
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Manage project work content
Capital source details
Medium-term public investment capital Provincial budget for the period 2021-2025: 1,000 million VND and for the period 2026-2030: 24,000 million VND.
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
8.Bidding package No. 3: Extracting measurements for land recovery and placing site clearance markers
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Extract measurement of land recovery
Capital source details
Medium-term public investment capital Provincial budget for the period 2021-2025: 1,000 million VND and for the period 2026-2030: 24,000 million VND.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Second contractor selection plan for project: Construction of flooded road from Quang Luu commune center to Quang Thach commune center connecting provincial road 22". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Second contractor selection plan for project: Construction of flooded road from Quang Luu commune center to Quang Thach commune center connecting provincial road 22" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 1

You did not use the site, Click here to remain logged. Timeout: 60 second