Bidder Selection Plan

Supplementing the plan to select the project contractor component 2: Building Ring 2 of the city, the section from Vo Nguyen Giap Street to Pham Van Dong Street.

  Watching      
Find: 09:36 17/10/2025
Contractor Selection Plan ID
PL2500162818-01
Publishing time
09:34 17/10/2025
Posting Status
Published
Contractor selection plan name
Supplementing the plan to select the project contractor component 2: Building Ring 2 of the city, the section from Vo Nguyen Giap Street to Pham Van Dong Street.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500016463-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group A
Project implementation time
5 Years
Authority that issues the decision
Ủy ban nhân dân Thành phố Hồ Chí Minh
Approval date
24/06/2025
Approval ID
3152/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 11
1.Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
730 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Implementation of works insurance according to current regulations.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
2.TV08: Construction supervision consultancy and construction equipment installation
Tender/ Prequalification Notice ID
Contract execution period
730 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out supervision of construction and installation of works equipment according to current regulations.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
3.TV09: Auditing Consulting
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Implement audit according to current regulations.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter I, 2027
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
4.TV10: Traffic safety verification advice before being put into operation
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Conduct traffic safety verification before putting the project into exploitation and use.
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2027
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
5.TV11: Advice on selecting audit consultancy contractors
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Making bidding documents and evaluating bidding documents for auditing consulting package
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter IV, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
6.XL01: Building parallel roads on both sides and Rach Ngang bridge
Tender/ Prequalification Notice ID
Contract execution period
660 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Organize the construction of parallel roads on both sides; sidewalk; surface drainage systems and wastewater; technical trenches, tunnen; The Rach Ngang bridge ... - Building the intersection with Kha Van Can street according to the design. - Producing and installing systems to ensure traffic safety in the exploitation phase (signs, mountain paints, price Long Mon ...) within the scope of the bidding package.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
7.XL02: Building overpass No. 1, overpass No. 2 and intersection architectural symbols
Tender/ Prequalification Notice ID
Contract execution period
660 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
-Organizing the construction of the overpass items No. 1 (including branch N1-1, branch N1-2), overpass No. 2. - Construction of barrier walls, two ends of the bridge to the end of the bread barrier ... - Organizing the construction of architectural symbols of Ring Ring 2 - Pham Van Dong; - Producing and installing systems to ensure traffic safety in the exploitation phase (signs, mountain paints, price Long Mon ...) within the scope of the bidding package.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
8.XL03: Building tunnel HC1, renovating and expanding Pham Van Dong road to the intersection
Tender/ Prequalification Notice ID
Contract execution period
660 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Organizing construction of underground tunnels; - Pumping stations, supply, installation of pumps, electrical systems, underground broth drainage pipes ... - Organizing the construction of Pham Van Dong Street within the intersection, sidewalk, drainage system, technical trench, manufacturing, installing systems to ensure traffic safety in the exploitation phase (signs, paint, dragonfield ...) within the scope of bidding package. - Relocating and returning existing techniques on Pham Van Dong street.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
9.XL04: Building and installing traffic lighting systems, traffic signals
Tender/ Prequalification Notice ID
Contract execution period
730 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Organize the installation of traffic lighting systems, traffic signals, optical signs, CCTV (including the relocation of existing lighting systems). - Installing the art lighting system - Pham Van Dong ...
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
10.XL05: Construction of trees, green areas, automatic watering system
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Organize the construction of trees, green areas, automatic watering systems, drilling wells to exploit groundwater to serve automatic irrigation systems, construction of water tanks ...
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
11.XL06: Implementation of trees handling plans
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Nursing and replanting and cutting trees under the plan to handle trees were united by the People's Committee of Thu Duc City in Document No. 12478/UBND-GTCC dated December 17, 2024.
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Supplementing the plan to select the project contractor component 2: Building Ring 2 of the city, the section from Vo Nguyen Giap Street to Pham Van Dong Street.". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Supplementing the plan to select the project contractor component 2: Building Ring 2 of the city, the section from Vo Nguyen Giap Street to Pham Van Dong Street." plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 50

You did not use the site, Click here to remain logged. Timeout: 60 second