Bidder Selection Plan

T1.2

  Watching      
Find: 10:02 09/02/2023
Contractor Selection Plan ID
PL2300012684-00
Publishing time
10:02 09/02/2023
Posting Status
Published
Contractor selection plan name
T1.2
Investment objective
Ensure living and working conditions for the unit
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300004636-01
Name of project
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
2 Years
Authority that issues the decision
Bộ Quốc Phòng
Approval date
03/02/2023
Approval ID
400/QĐ-BQP
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Filter name, Total investment, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 8
1.Bidding Package 07: Consultancy on preparation of Bid Documents to evaluate bid packages
Tender/ Prequalification Notice ID
Contract execution period
720 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thanh Trì District, Hà Nội
2.Package 06: Consultancy on verification of TKBVTC-TDT
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thanh Trì District, Hà Nội
3.Package 14: Construction, supply and installation of equipment, tools, anti-termites in 5-storey army house; technical maintenance and repair areas and ancillary infrastructure systems.
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thanh Trì District, Hà Nội
4.Package 12: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
720 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thanh Trì District, Hà Nội
5.Package 15: Supply and installation of 250KVA substation, 3x185mm2 underground cable and 250KVA generator
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thanh Trì District, Hà Nội
6.Tender package No 11: Audit
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thanh Trì District, Hà Nội
7.Tender package No 09: Cost of pile testing
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thanh Trì District, Hà Nội
8.Tender package No 10: Equipment appraisal consulting
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thanh Trì District, Hà Nội

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "T1.2". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "T1.2" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 13

You did not use the site, Click here to remain logged. Timeout: 60 second