Bidder Selection Plan

Technical economic report and plan for selecting construction contractors: Building a record storage warehouse at the Social Insurance of Dak Mil district, Dak Nong province

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 11:21 19/10/2023
Contractor Selection Plan ID
PL2300195651-00
Publishing time
11:20 19/10/2023
Posting Status
Published
Contractor selection plan name
Technical economic report and plan for selecting construction contractors: Building a record storage warehouse at the Social Insurance of Dak Mil district, Dak Nong province
Procurement name
Technical economic report and plan for selecting construction contractors: Building a record storage warehouse at the Social Insurance of Dak Mil district, Dak Nong province
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Shopping budget
To view full information, please Login or Register
Spending Category
Mandatory spending
Authority that issues the decision
Bảo hiểm xã hội tỉnh Đắk Nông
Approval date
17/10/2023
Approval ID
593/QĐ-BHXH
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 6
1.Expenses for appraisal of bidding documents and results of selection of construction contractors
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Expenses for management of Social Insurance, Health Insurance, Unemployment Insurance.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location
2.Construction supervision cost
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Expenses for management of Social Insurance, Health Insurance, Unemployment Insurance.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location
3.Cost audit
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Expenses for management of Social Insurance, Health Insurance, Unemployment Insurance.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location
4.Cost of Elaboration of Bid, Evaluation of Bid for construction
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Expenses for management of Social Insurance, Health Insurance, Unemployment Insurance.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location
5.Cost of Project Management Consulting
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Expenses for management of Social Insurance, Health Insurance, Unemployment Insurance.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location
6.Construction
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Expenses for management of Social Insurance, Health Insurance, Unemployment Insurance.
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Technical economic report and plan for selecting construction contractors: Building a record storage warehouse at the Social Insurance of Dak Mil district, Dak Nong province". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Technical economic report and plan for selecting construction contractors: Building a record storage warehouse at the Social Insurance of Dak Mil district, Dak Nong province" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 13

You did not use the site, Click here to remain logged. Timeout: 60 second