Bidder Selection Plan
Thanh Loc kindergarten
Contractor Selection Plan ID
PL2400097345-00
Publishing time
10:53 03/06/2024
Contractor selection plan name
Thanh Loc kindergarten
Investment objective
Gradually create adequate facilities as well as learning and teaching equipment for teachers and students of the school
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400026836-00
Spending Category
Investment and Development Spending
Project implementation time
2 Years
Authority that issues the decision
UBND huyện Giồng Riềng
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent . DauThau.info supports downloading on most modern browsers and devices! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 11
Tender/ Prequalification Notice ID
Contract execution period
75 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Bid cost, Bid evaluation
Capital source details
Lottery capital source
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Cost of material appraisal
Capital source details
Lottery
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
75 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Insurance cost
Capital source details
Lottery
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Equipment monitoring costs
Capital source details
Lottery
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Cost audit
Capital source details
Lottery
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction supervision cost
Capital source details
Lottery
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Cost of preparing bidding documents and evaluating equipment bidding documents
Capital source details
Lottery
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
construction insurance costs
Capital source details
Lottery
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction Costs
Capital source details
Lottery
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Provincial testing costs
Capital source details
Lottery
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Equipment cost
Capital source details
Lottery
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Thanh Loc kindergarten". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email
To be one of the
first to receive email notifications of contractor selection plans similar to the "Thanh Loc kindergarten" plan as soon as they are posted,
sign up for DauThau.info's VIP 2 plan.