Bidder Selection Plan

The contractor selection plan to prepare to design construction drawings - Construction cost estimates (phase I) Project: Construction of Economic Auction HTD Land Land Land Auction A1, Tien Duong Commune, Dong Anh District

  Watching      
Find: 09:59 18/09/2025
Contractor Selection Plan ID
PL2500226133-00
Publishing time
09:57 18/09/2025
Posting Status
Published
Contractor selection plan name
The contractor selection plan to prepare to design construction drawings - Construction cost estimates (phase I) Project: Construction of Economic Auction HTD Land Land Land Auction A1, Tien Duong Commune, Dong Anh District
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500048699-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
4 Years
Authority that issues the decision
Ban quản lý Dự án đầu tư - hạ tầng xã Phúc Thịnh
Approval date
17/09/2025
Approval ID
471/QĐ-BQLDA
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 8
1.Bidding package 1: Survey of construction drawing design
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Geological terrain survey for the design of BVTC
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Tender package No 2: Consulting and supervision of package No. 1
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction survey in service of construction drawing design
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.Package 3: Design consultancy for construction drawings - cost estimate
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Establishment of construction drawings - Total construction construction estimates (phase I)
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Tender package No 4: Examination of construction drawing design - estimation
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Examination of construction drawing drawing - Construction construction cost estimates (phase I)
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Tender package No 5: Making Bidding Documents, evaluating Bid Bids Tender package No 3
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Evaluation of Bidding Bidding, evaluation of Bid Bids Package of construction drawing design consultancy
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
6.Bidding package 6: Evaluation of Bidding Documents, Evaluation of Code of Bidding Tender package No 3
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Evaluation of Bidding Documents, Evaluation of Code of Consulting Package for Construction Drawing Design Consulting
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
7.Bidding package 7: Plug the boundary landmark for land clearance
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Plug the boundaries to determine the boundaries according to the guidance of the Department of Agriculture and Environment to serve the land clearance
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
8.Bidding package 8: Pricing advice
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Determine the price of construction materials not in the price announcement of materials
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "The contractor selection plan to prepare to design construction drawings - Construction cost estimates (phase I) Project: Construction of Economic Auction HTD Land Land Land Auction A1, Tien Duong Commune, Dong Anh District". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "The contractor selection plan to prepare to design construction drawings - Construction cost estimates (phase I) Project: Construction of Economic Auction HTD Land Land Land Auction A1, Tien Duong Commune, Dong Anh District" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 7

You did not use the site, Click here to remain logged. Timeout: 60 second