The plan for selecting contractors in the construction investment project of upgrading the ring road of Mu Cang Chai town, Mu Cang Chai district, Yen Bai province (phase 2)
The plan for selecting contractors in the construction investment project of upgrading the ring road of Mu Cang Chai town, Mu Cang Chai district, Yen Bai province (phase 2)
Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info. Our system will help you download files faster, on any device without installing Client Agent. To download, please Login or Register
1315 QD.pdf
List of Bid:
Number of packages: 6
1.Package 08: Consulting on setting up bidding documents, evaluating bids for construction bidding packages, consulting on construction supervision for upgrading the ring road of Mu Cang Chai town, Mu Cang Chai district, Yen Bai province
Capital from the provincial budget, from the district budget
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
All in one
Prequalification
No
Location
2.Tender package No 09: Construction of upgrading the ring road of Mu Cang Chai town, Mu Cang Chai district, Yen Bai province (Km0 +:- Km0+541.27 + Item to move electric lines)
Capital from the provincial budget, from the district budget
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
According to the adjusted unit price
Prequalification
No
Location
3.Package 10: Construction of upgrading the ring road of Mu Cang Chai town, Mu Cang Chai district, Yen Bai province (Ly Trinh Km0+541.27 -:- Km1+385.7m)
Capital from the provincial budget, from the district budget
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
According to the adjusted unit price
Prequalification
No
Location
4.Package 11: Construction and construction of upgrading the ring road of Mu Cang Chai town, Mu Cang Chai district, Yen Bai province (Lyricist Km1+385.7m -:- Km4+225.95m)
Capital from the provincial budget, from the district budget
Contractor Selection Type
Appointed contractors, no domestic pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
All in one
Prequalification
No
Location
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "The plan for selecting contractors in the construction investment project of upgrading the ring road of Mu Cang Chai town, Mu Cang Chai district, Yen Bai province (phase 2)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "The plan for selecting contractors in the construction investment project of upgrading the ring road of Mu Cang Chai town, Mu Cang Chai district, Yen Bai province (phase 2)" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.