There has been a decision to approve the investment project
Approval date
15/01/2020
Approval ID
Số: 01.20-HH1,HH2/QĐ-TPC
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
Quyet dinh so 01.20-HH1 HH2 QD - TPC.pdf
List of Bid:
Number of packages: 12
1.Prepare bidding documents for evaluation of construction bids + Prepare bid documents for evaluation of equipment bids (underground construction, body construction, completion, Golden Land 5 project, HH1, HH2 apartment building, outdoor infrastructure) + Prepare bidding documents and evaluate bids for consultancy bidding packages for supervision of construction and installation parts + Prepare bidding documents and evaluate bids for equipment supervision consultancy bidding packages (underground construction, construction construction of the body, completion of the Golden Land 5 Project, construction of HH1, HH2 apartment buildings, outdoor infrastructure)
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2020
Contract Type
All in one
Prequalification
No
Implementation location
9.Appraisal of bidding documents, HSYC for construction and installation bidding packages and equipment bidding packages (including construction and supervision) + Appraisal of results of selection of contractors for construction and installation bidding packages and equipment bidding packages. (including construction and supervision)
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Implementation location
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "The plan for selecting contractors to implement the project for the 4th time". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "The plan for selecting contractors to implement the project for the 4th time" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.