Bidder Selection Plan

The plan to select contractors for the construction of new classrooms of Dao Long Primary School (classroom items of 05 rooms)

  Watching      
Find: 09:25 15/02/2022
Contractor selection plan ID
20220214519-00
Publication date
09:20 15/02/2022
Publication status
Actual notification
Contractor selection plan name
The plan to select contractors for the construction of new classrooms of Dao Long Primary School (classroom items of 05 rooms)
Investor
Ban quản lý dự án đầu tư xây dựng thành phố Phan Rang - Tháp Chàm
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20211033514-00
Name of project
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
10/02/2022
Approval ID
Số 401/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

List of Bid:
Number of packages: 8
1.Package 05: Prepare bidding documents and analyze and evaluate bids for construction works
Tender/ Prequalification Notice ID
Contract Period
32 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
According to Decision No. 2692/QD-UBND dated December 30, 2021 of the People's Committee of Phan Rang - Thap Cham city on the assignment of development investment plan in 2022
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
2.Package 06: Evaluation of bidding documents and results of selection of construction contractors
Tender/ Prequalification Notice ID
Contract Period
10 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
According to Decision No. 2692/QD-UBND dated December 30, 2021 of the People's Committee of Phan Rang - Thap Cham city on the assignment of development investment plan in 2022
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
3.Package 07: Supervision of construction works
Tender/ Prequalification Notice ID
Contract Period
210 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
According to Decision No. 2692/QD-UBND dated December 30, 2021 of the People's Committee of Phan Rang - Thap Cham city on the assignment of development investment plan in 2022
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
4.Package 08: Appraisal of construction equipment
Tender/ Prequalification Notice ID
Contract Period
15 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
According to Decision No. 2692/QD-UBND dated December 30, 2021 of the People's Committee of Phan Rang - Thap Cham city on the assignment of development investment plan in 2022
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
Contract Type
All in one
Prequalification
No
Location
5.Package 09: Inspection of construction materials
Tender/ Prequalification Notice ID
Contract Period
210 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
According to Decision No. 2692/QD-UBND dated December 30, 2021 of the People's Committee of Phan Rang - Thap Cham city on the assignment of development investment plan in 2022
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
6.Package 10: Construction insurance
Tender/ Prequalification Notice ID
Contract Period
210 days
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
According to Decision No. 2692/QD-UBND dated December 30, 2021 of the People's Committee of Phan Rang - Thap Cham city on the assignment of development investment plan in 2022
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
7.Tender package No 11: Construction work
Tender/ Prequalification Notice ID
Contract Period
210 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
According to Decision No. 2692/QD-UBND dated December 30, 2021 of the People's Committee of Phan Rang - Thap Cham city on the assignment of development investment plan in 2022
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
8.Package 12: Supply and installation of construction equipment
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Goods
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
According to Decision No. 2692/QD-UBND dated December 30, 2021 of the People's Committee of Phan Rang - Thap Cham city on the assignment of development investment plan in 2022
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "The plan to select contractors for the construction of new classrooms of Dao Long Primary School (classroom items of 05 rooms)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "The plan to select contractors for the construction of new classrooms of Dao Long Primary School (classroom items of 05 rooms)" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 18

You did not use the site, Click here to remain logged. Timeout: 60 second