Bidder Selection Plan

The plan to select the contractor for the 1st phase of the project of Installing 110kV crossroads to An Don at the 220kV Ngu Hanh Son substation

  Watching      
Find: 00:41 11/04/2021
Contractor selection plan ID
20210425759-00
Publication date
20:32 10/04/2021
Publication status
Actual notification
Contractor selection plan name
The plan to select the contractor for the 1st phase of the project of Installing 110kV crossroads to An Don at the 220kV Ngu Hanh Son substation
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20210425758-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been no decision to approve the investment project
Location
Approval date
30/03/2021
Approval ID
511/QĐ-PTC2
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

List of Bid:
Number of packages: 1
1.Tender package No 1 Providing consulting services for preparing economic and technical reports and bidding documents
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Own capital of EVNNPT
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2021
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "The plan to select the contractor for the 1st phase of the project of Installing 110kV crossroads to An Don at the 220kV Ngu Hanh Son substation". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "The plan to select the contractor for the 1st phase of the project of Installing 110kV crossroads to An Don at the 220kV Ngu Hanh Son substation" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 19

You did not use the site, Click here to remain logged. Timeout: 60 second