Bidder Selection Plan

The preparation step to invest in the project of expanding land to build a training field

  Watching  
Project Contractor selection plan Bid award
Find: 09:32 21/06/2023
Contractor Selection Plan ID
PL2300100030-00
Publishing time
09:25 21/06/2023
Posting Status
Published
Contractor selection plan name
The preparation step to invest in the project of expanding land to build a training field
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300027324-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
1 Years
Location
Authority that issues the decision
Lữ đoàn 131
Approval date
06/04/2023
Approval ID
648/QĐ-LĐ
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 2
1.Tender package TV-02: Consulting for making environmental impact assessment reports
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
State budget for regular spending on National Defense
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
An Dương District, Hải Phòng
2.Tender package TV-01: Consulting on making topographic survey, planning 1/500, making feasibility study report
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
State budget for regular spending on National Defense
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
An Dương District, Hải Phòng

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "The preparation step to invest in the project of expanding land to build a training field". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "The preparation step to invest in the project of expanding land to build a training field" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 3

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8849 Projects are waiting for contractors
  • 1242 Tender notices posted in the last 24 hours
  • 1874 Contractor selection plan posted in the last 24 hours
  • 25500 Tender notices posted in the past month
  • 39868 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second