Bidder Selection Plan

Upgrading and renovating roads to build a model new rural commune in Du Le commune, Kien Thuy district

  Watching      
Find: 17:56 29/08/2023
Contractor Selection Plan ID
PL2300118817-02
Publishing time
17:55 29/08/2023
Posting Status
Published
Contractor selection plan name
Upgrading and renovating roads to build a model new rural commune in Du Le commune, Kien Thuy district
Investment objective
In order to complete the traffic criteria in the model new rural criteria set in the commune. Step by step, build and develop the road network in the area, connecting the internal road system with the district's traffic network; improve the infrastructure and living conditions of the community in the area. Serving the goals of socio-economic development, contributing to improving the environment and landscape, and creating favorable conditions to attract investors in the fields of industry, tourism and
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300032046-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Location
Authority that issues the decision
UBND huyện Kiến Thụy
Approval date
29/08/2023
Approval ID
3385/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date, Bidding package information (View changes)

- Change: Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 11
1.Package 15: Construction and installation
Tender/ Prequalification Notice ID
Contract execution period
350 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
Fixed unit price
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
2.Package 07: Checking the cadastral measurement excerpt
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
3.Package 02: Evaluation of EHSMT and results of contractor selection for bidding packages
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
4.Package 03: Design of construction drawings, total cost estimate
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
5.Package 04: Supervising and surveying the construction drawing design step
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
6.Package 05: Verification of construction drawing design and total cost estimate
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
7.Package 14: Insurance
Tender/ Prequalification Notice ID
Contract execution period
350 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
8.Package 08: Supervision of construction works
Tender/ Prequalification Notice ID
Contract execution period
350 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
9.Tender package No 01: E-HSMT preparation and E-HSDT evaluation of bidding packages
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
10.Package 06: Cadastral mapping
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng
11.Package 09: Independent audit
Tender/ Prequalification Notice ID
Contract execution period
350 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City budget + District budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
Kiến Thuỵ District, Hải Phòng

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Upgrading and renovating roads to build a model new rural commune in Du Le commune, Kien Thuy district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Upgrading and renovating roads to build a model new rural commune in Du Le commune, Kien Thuy district" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 5

You did not use the site, Click here to remain logged. Timeout: 60 second