Bidder Selection Plan

Urban planning project Upgrading Hoc Mon irrigation system - Bac Binh Chanh (project implementation phase)

  Watching      
Find: 15:30 16/07/2024
Contractor Selection Plan ID
PL2400138719-00
Publishing time
15:29 16/07/2024
Posting Status
Published
Contractor selection plan name
Urban planning project Upgrading Hoc Mon irrigation system - Bac Binh Chanh (project implementation phase)
Investment objective
- Ensuring irrigation, preventing saltwater intrusion, channeling fresh water to wash away alum, draining waterlogging, improving the environment, and preventing floods for agricultural production and rural development, contributing to preventing and mitigating natural disasters for about 20,356 hectares of natural land, in That is 8,300 hectares of arable land of all kinds. - Combine the development of in-field traffic to serve production and socio-economic development in a multi-sectoral, multi-target direction (urban agriculture, industry, people's livelihood, new rural construction) and at the same time adapt to climate change conditions of sea level rise.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400032812-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
4 Years
Authority that issues the decision
Sở Nông nghiệp và Phát triển nông thôn
Approval date
10/07/2024
Approval ID
303/QĐ-SNN
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 24
1.Bidding package TV-7: Consulting on preparing bidding documents, request documents, evaluating bid documents, proposal documents for bidding package TV-11; PTV-3
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Carry out tasks under the responsibility of the Bidding Party. - Carry out the work of preparing Bidding Documents, Proposal Documents and evaluating Bidding Documents and Proposals. - Report and submit to the investor the results of contractor selection
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
2.Bidding package TV-8: Consulting on preparing bidding documents, evaluating bidding documents for bidding packages: TV-16; TV-17; XL-1; XL-2; XL-3; XL-4; XL-5; XL-6; PTV-1; PTV-2.
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Carry out tasks under the responsibility of the Bidding Party. - Carry out the work of preparing bidding documents and evaluating bidding documents. - Report and submit to the investor the results of contractor selection.
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
3.Bidding package TV-9: Consulting on preparing bidding documents, evaluating bidding documents for bidding packages: TV-20, PTV-4
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Carry out tasks under the responsibility of the Bidding Party. - Carry out the work of preparing bidding documents and evaluating bidding documents. - Report and submit to the investor the results of contractor selection.
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
4.Package TV-10: Consulting on setting up construction survey tasks and implementing them after basic design
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Establish tasks and estimates for construction surveys and implementation after basic design according to current regulations
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
5.Package TV-11: Construction survey consulting, construction design and implementation after basic design
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
'- Prepare a technical plan for construction survey - Carry out survey work - Report on construction survey results - Prepare design and construction estimates for projects implemented after basic design. - Prepare a plan to place markers demarcating the scope of protection of irrigation works.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
Package and Fixed Price
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
6.Package TV-12: Consulting on supervision of construction survey and implementation after basic design
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Check the actual capacity of construction survey contractors - Supervise the implementation of survey work until completion - Report on construction survey supervision results.
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
7.Bidding package TV-13: Consulting on verification of construction design and construction estimates
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Verify construction drawing designs and estimates according to current legal regulations. - Report on inspection results.
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
8.Package TV-14: Survey consulting, construction technical plans and estimates for mine and explosives clearance
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Investigate, survey, prepare technical construction plans and estimates for clearance of bombs, mines and explosives.
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
9.Bidding package TV-15: PTV-3 supervision consulting
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Supervise the construction of bomb, mine and explosive material clearance. - Reporting monitoring results.
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
10.Package TV-16: Construction Supervision Consulting for XL-1 package; XL-2
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Carry out construction supervision in terms of quality, volume, progress, labor safety, and environmental protection according to approved design documents and current regulations. - Content of supervision according to Clause 1, Article 19 of Decree No. 06/2021/ND-CP. - Report monitoring results periodically.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
11.Package TV-17: Construction Supervision Consulting for XL-3 package; XL-4; XL-5
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Carry out construction supervision in terms of quality, volume, progress, labor safety, and environmental protection according to approved design documents and current regulations. - Content of supervision according to Clause 1, Article 19 of Decree No. 06/2021/ND-CP. - Report monitoring results periodically.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
12.Package TV-18: Construction Supervision Consulting for package XL-6.
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Carry out construction supervision in terms of quality, volume, progress, labor safety, and environmental protection according to approved design documents and current regulations. - Content of supervision according to Clause 1, Article 19 of Decree No. 06/2021/ND-CP. - Report monitoring results periodically.
Capital source details
City Budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
13.Package TV-19: Consulting on equipment price appraisal.
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraise equipment prices according to current regulations
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
14.Package TV-20: Construction audit consulting
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Check project legal documents; Investment capital sources; Investment costs and other related work. - Analyze, evaluate and synthesize audit results. - Prepare audit reports. - Handle tasks that arise after issuing the audit report.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
15.Package XL-1: Dredging 3 lines and embanking 6 lines.
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out dredging of TTN, T10, AH-KC canals and embankment of AH14 canal; T6; T3; NT3, Long An Ranh (section from TL9 - Thay Cai canal; Long An Ranh (section from TL10-TL9).
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
16.Package XL-2: Dredging 7 canals and embanking 3 canals
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out dredging work on 7 C17 canal routes; C19; C20; C23; C24; C25; Canal A and embankment of 3 Lien Region canals; C19; C20
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
17.Package XL-3: Construction of 4 culverts at the beginning and end of the canal; Hoist to lift and lower the valve gate (culvert at the end of canal AH14)
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out construction of culvert at the beginning of canal C18, at the end of canal C18, at the beginning of canal B16, at the end of canal AH14; Hoist to lift and lower the valve gate (culvert at the end of canal AH14).
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
18.Package XL-4: Supply, fabricate, install valve gates and repair pump stations; The machine opens and closes the valve door, vacuum priming pump
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carrying out the work of upgrading and replacing 59 valve gates and 57 valve slots; Repair, 5 pumping stations: T1, T3, T5, T7, T9; The machine opens and closes the valve door, vacuum priming pump.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
19.Package XL-5: Repairing traffic bridges on culverts
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out repair work on 02 traffic bridges on culverts: Traffic bridge on Tan Kien culvert and on the culvert at the end of Long An Ranh Canal.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
20.Package XL-6: Construction and supply and installation of monitoring systems, monitoring water levels, water quality and some automatic meteorological elements.
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carrying out the construction of equipment storage cabinets and providing and installing an automatic water level monitoring system, water quality and some meteorological factors (rain, temperature) to serve the public. management, operation and regulation of irrigation systems.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
21.PTV-1 bidding package: Insurance for all construction risks for XL-1 bidding packages; XL-2.
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance for all construction risks for XL-1 bidding packages; XL-2.
Capital source details
city budget
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
22.Bidding package PTV-2: Insurance for all construction risks for bidding package No. XL-3; XL-4; XL-5; XL-6
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance for all construction risks for XL-3 bidding packages; XL-4; XL-5; XL-6.
Capital source details
city budget
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
23.Package PTV-3: Construction of clearance and disposal of bombs, mines and explosives.
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out clearance and disposal of bombs, mines and explosives according to the approved plan.
Capital source details
city budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city
24.Package PTV-4: Installing markers demarcating the protection scope of irrigation works
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Implement landmarks demarcating the scope of protection of irrigation works according to the approved plan and current regulations
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Hóc Môn District, TP.Hồ Chí Minh
Implementation location (Before merge)
Ho Chi Minh city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Urban planning project Upgrading Hoc Mon irrigation system - Bac Binh Chanh (project implementation phase)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Urban planning project Upgrading Hoc Mon irrigation system - Bac Binh Chanh (project implementation phase)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 144

You did not use the site, Click here to remain logged. Timeout: 60 second