Bidder Selection Plan
Western Ring Road (section through the Centralized Information Technology Park) THDT
Contractor Selection Plan ID
PL2300070706-00
Publishing time
11:16 15/05/2023
Contractor selection plan name
Western Ring Road (section through the Centralized Information Technology Park) THDT
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300020160-00
Spending Category
Investment and Development Spending
Project implementation time
4 Years
Authority that issues the decision
UBND thành phố Đà Nẵng
Approval ID
Số 967/QĐ-UBND ngày 12/05/2023
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent . DauThau.info supports downloading on most modern browsers and devices! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 14
1. Surveying, making plans and cost estimates for mine clearance construction
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Tender/ Prequalification Notice ID
Contract execution period
570 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
According to adjusted unit price
4. Consultancy and verification of surveying tasks, survey estimates, survey supervision of construction drawing design steps
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
5. Consulting on planning for environmental protection
Tender/ Prequalification Notice ID
Contract execution period
105 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
6. Consulting on setting up survey tasks for construction drawing steps
Tender/ Prequalification Notice ID
Contract execution period
80 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
7. Consulting and surveying the design and construction drawing steps
Tender/ Prequalification Notice ID
Contract execution period
105 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
8. Consultancy, design verification, construction drawing estimation
Tender/ Prequalification Notice ID
Contract execution period
75 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
9. Consulting to design construction drawings for traffic and technical infrastructure
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q2 2023
Type of contract
All in One
10. Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
935 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
11. Consulting on cadastral mapping for compensation and site clearance
Tender/ Prequalification Notice ID
Contract execution period
105 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
12. Construction of clearing mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
105 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
13. Supervision and inspection of construction quality of mines and explosives clearance
Tender/ Prequalification Notice ID
Contract execution period
105 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
14. Consulting on traffic safety inspection before putting the project into operation
Tender/ Prequalification Notice ID
Contract execution period
75 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Western Ring Road (section through the Centralized Information Technology Park) THDT". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email
To be one of the
first to receive email notifications of contractor selection plans similar to the "Western Ring Road (section through the Centralized Information Technology Park) THDT" plan as soon as they are posted,
sign up for DauThau.info's VIP 2 plan.