Data analysis results of DauThau.info software for bid solicitors UBND xã Ba Vì as follows:
- Has relationships with 1 project owners.
- Has relationships with 20 contractor.
- Announced 31 investment development project, of which 1 projects have not yet announced the prequalification documents.
- Announced 3 contractor selection plans with a total of 15 bidding packages, of which 0 prequalification documents have not found the investment project.
- Has invited bids for 0 packages (with 0 tender notices), and conducted prequalification for 0 packages.
- There are 0 bidding packages with content that needs clarification.
- Announced the results of 2 package, and canceled bids for 0 packages (among the packages mentioned above).
- There are 0 packages with results that do not have tender notice or prequalification notice.
- There are 0 packages with results that do not have Contractor selection plan.
- There are 14 packages that have not fully posted the contractor selection results. Of these 14 bidding packages have no tender notices found.
- On average, the number of contractors participating in each package is: 0 contractors.
- Breakdown by bidding field: Goods 0%, Construction 0%, Consultancy 0%, Non-consultancy 0%, Mixed 0%, Other fields 0%.
- The total value according to the packages with valid contractor selection results is: 112,704,281 VND, of which the total winning bid value is: 112,704,000 VND.
- The savings rate is: 0.00%.
Data analysis results of DauThau.info software for bid solicitors UBND xã Ba Vì as follows:
- Has relationships with 20 contractor.
- The average number of contractors participating in each bidding package is: 0 contractors.
- Proportion of bidding fields: Goods 0%, Construction 0%, Consulting 0%, Non-consulting 0%, Mixed 0%, Other 0%.
- The total value according to the bidding package with valid IMP is: 112,704,281 VND, in which the total winning value is: 112,704,000 VND.
- The savings rate is: 0.00%.
This Bid solicitor is also an investor. The analysis results of data for the investor UBND xã Ba Vì are as follows:
- Is the investor of 31 development investment projects.
- Is the investor of 36 contractor selection plans, of which 3 were self-published, and 33 were published by other entities.
- Is the investor of 4 Tender Notices, of which 0 were self-invited, and 4 were invited by other entities.
| Evaluation criteria | Evaluation score |
|---|---|
| Experience | ??? |
| Financial capacity | ??? |
| Transparency of the investor/bidder | ??? |
| Bidding efficiency | ??? |
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Renovating and upgrading road surfaces and drainage systems in the villages of Pheo, Xuan Tho, Khanh Chuc Bai, Son Ha, Moc with 2 bidding package .
07/01/2026 11:14
Investor UBND xã Ba Vì has posted an investment and development project Renovating and upgrading road surfaces and drainage systems in the villages of Pheo, Xuan Tho, Khanh Chuc Bai, Son Ha, Moc.
07/01/2026 11:11
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Renovating and upgrading irrigation and drainage canals combined with in-field roads in the villages of Go Da Che and Go Dinh Muon with 3 bidding package .
07/01/2026 11:03
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Renovating and upgrading Minh Quang A Primary School with 1 bidding package .
07/01/2026 10:44
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Adding teaching equipment, boarding, smart classrooms, digital conversion equipment and AI applications, familiarization, teaching in English for schools in the commune with 3 bidding package .
07/01/2026 10:36
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Build a new recording studio and renovate the commune radio system with 3 bidding package .
07/01/2026 10:26
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Renovating and upgrading Sui Quan Bridge with 3 bidding package .
07/01/2026 10:16
Investor UBND xã Ba Vì has posted an investment and development project Renovate and upgrade Sui Quan Bridge.
07/01/2026 10:10
Investor UBND xã Ba Vì has posted an investment and development project Build a new recording studio and renovate the commune radio system.
07/01/2026 10:10
Investor UBND xã Ba Vì has posted an investment and development project Additional teaching equipment, boarding, smart classrooms, digital conversion equipment and AI applications, familiarization, teaching in English for schools in the commune.
07/01/2026 10:10
The data sheet has been partially hidden, to see the full information please Login or Register
UBND xã Ba Vì announced the results of the bid package Package No. 12: Static compression of piles .
- Winning bidder: CÔNG TY TNHH QAVN
18/12/2025 10:05
UBND xã Ba Vì publishes the plan Project contractor selection plan: Construction and expansion of Minh Quang High School with 6 bidding package .
18/12/2025 09:53
UBND xã Ba Vì publishes the plan Additional contractor selection plan with 5 bidding package .
17/11/2025 10:53
UBND xã Ba Vì publishes the plan Supplementing the project contractor selection plan: Renovating and upgrading Cau Chua canal to Song Da (Moc village), Minh Quang commune, Ba Vi district with 4 bidding package .
29/09/2025 11:04
The data sheet has been partially hidden, to see the full information please Login or Register
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Renovating and upgrading road surfaces and drainage systems in the villages of Pheo, Xuan Tho, Khanh Chuc Bai, Son Ha, Moc with 2 bidding package .
07/01/2026 11:14
Investor UBND xã Ba Vì has posted an investment and development project Renovating and upgrading road surfaces and drainage systems in the villages of Pheo, Xuan Tho, Khanh Chuc Bai, Son Ha, Moc.
07/01/2026 11:11
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Renovating and upgrading irrigation and drainage canals combined with in-field roads in the villages of Go Da Che and Go Dinh Muon with 3 bidding package .
07/01/2026 11:03
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Renovating and upgrading Minh Quang A Primary School with 1 bidding package .
07/01/2026 10:44
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Adding teaching equipment, boarding, smart classrooms, digital conversion equipment and AI applications, familiarization, teaching in English for schools in the commune with 3 bidding package .
07/01/2026 10:36
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Build a new recording studio and renovate the commune radio system with 3 bidding package .
07/01/2026 10:26
UBND xã Ba Vì publishes the plan Contractor selection plan for project preparation phase: Renovating and upgrading Sui Quan Bridge with 3 bidding package .
07/01/2026 10:16
Investor UBND xã Ba Vì has posted an investment and development project Renovate and upgrade Sui Quan Bridge.
07/01/2026 10:10
Investor UBND xã Ba Vì has posted an investment and development project Build a new recording studio and renovate the commune radio system.
07/01/2026 10:10
Investor UBND xã Ba Vì has posted an investment and development project Additional teaching equipment, boarding, smart classrooms, digital conversion equipment and AI applications, familiarization, teaching in English for schools in the commune.
07/01/2026 10:10
The data sheet has been partially hidden, to see the full information please Login or Register
To receive this bid solicitor's earliest contractor selection plan by email, please create register for the VIP2 package.
Summary: The bid solicitor’s UBND xã Ba Vì has posted 3 of the contractor selection plan, which contains 15 of the bidding package. See full list here
Summary: The Bid solicitor UBND xã Ba Vì has posted 2 contractor selection result in which:The data sheet has been partially hidden, to see the full information please Login or Register
- Published the results of the 2 package, canceled the bid 0 package (among the bidding packages above).
- There are 0 packages with no results found tender notice, Prequalifying Invitation Notice.
Summary: The Bid solicitor UBND xã Ba Vì has a relationship with 20 contractors. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: The Bid solicitor UBND xã Ba Vì has a relationship with 8 consulting units. The data sheet has been partially hidden, to see the full information please Login or Register
Summary: The procuring entity UBND xã Ba Vì has a relationship with 1 investors. The data sheet has been partially hidden, to see the full information please Login or Register
If you are still not our member, please sign up.You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!
Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.
When does contract negotiation fail?
[VIDEO] Guide for bid solicitors to Extend the Bid Submission Deadline
[VIDEO] Guide to Evaluating Bid Documents on the New National Bidding Network System
[VIDEO] Guide to Posting Tender Notices for PPP Projects
[VIDEO] Guide to Posting Prequalification Notices for PPP Projects
[VIDEO] Guide to Responding to Clarification Requests for e-HSMST (E-Prequalification Invitation Documents) of PPP Projects on the New National Bidding Network System
[VIDEO] Guide to Uploading the Shortlist for PPP Projects
[VIDEO] Guide for Bid Solicitors to Extend the Prequalification Document Submission Date for PPP Projects