Construction

Tender ID
Views
6
Contractor selection plan ID
Bidding package name
Construction
Bidding method
Online bidding
Tender value
81.443.630.961 VND
Estimated price
49.030.145.000 VND
Publication date
15:42 06/08/2025
Contract Type
Fixed unit price
Domestic/ International
Domestic
Contractor Selection Method
Single Stage Single Envelope
Fields
Constructions
Approval ID
06/QĐ-BQLDAĐTHT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Decision-making agency
Management Board of Investment - Infrastructure of Hoan Kiem Ward
Approval date
29/07/2025
Tendering result
There is a winning contractor
List of successful bidders
Number Business Registration ID ( on new Public Procuring System) Consortium Name Contractor's name Bid price Technical score Winning price Delivery time (days) Contract date
1 vn0100105172 Liên danh CSC-59-TVX

CONSTRUCTION TRANSPORTATION PUBLIC WORKS JOINT STOCK COMPANY

48.403.197.398,285 VND 48.403.197.000 VND 300 day
2 vn0300536017 Liên danh CSC-59-TVX

59 ONE MEMBER LIMITED LIABILITY COMPANY

48.403.197.398,285 VND 48.403.197.000 VND 300 day
3 vn0102400141 Liên danh CSC-59-TVX

THAO VIEN GREEN - UDIC JOINT STOCK COMPANY

48.403.197.398,285 VND 48.403.197.000 VND 300 day
The system analyzed and found the following joint venture contractors:
List of unsuccessful bidders:
Number Business Registration ID ( on new Public Procuring System) Consortium Name Contractor's name Reason for failure
1 vn0101309193 Liên danh Công ty cổ phần đầu tư thương mại và xây dựng đô thị Hà Nội và Công ty cổ phần tập đoàn đầu tư công nghệ Nam Long HA NOI URBAN CONSTRUCTION AND TRADE INVESTMENT JOINT STOCK COMPANY Assessment of capacity and experience. Failed; Technical evaluation. Unsatisfied (Specifically, Section 1. The level of meeting the technical requirements of construction materials and equipment: The contractor does not have a list of categories, types, standards, origin, specifications of equipment; there is no commitment to use materials, materials and equipment to meet the technical requirements and quality in the design documents and chapter V of E -HSMT. - Section 2. Provisions of the Construction Law ”. - Section 3. Measures to organize construction: + Part 3.1. Construction organization: Construction and installation items: Contractors propose solutions and anti -termite measures that are not suitable to the scope of the bidding package. + Part 3.2.
2 vn0313339640 Liên danh Công ty cổ phần đầu tư thương mại và xây dựng đô thị Hà Nội và Công ty cổ phần tập đoàn đầu tư công nghệ Nam Long NAM LONG TECHNOLOGY INVESTMENT GROUP JOINT STOCK COMPANY Assessment of capacity and experience. Failed; Technical evaluation. Unsatisfied (Specifically, Section 1. The level of meeting the technical requirements of construction materials and equipment: The contractor does not have a list of categories, types, standards, origin, specifications of equipment; there is no commitment to use materials, materials and equipment to meet the technical requirements and quality in the design documents and chapter V of E -HSMT. - Section 2. Provisions of the Construction Law ”. - Section 3. Measures to organize construction: + Part 3.1. Construction organization: Construction and installation items: Contractors propose solutions and anti -termite measures that are not suitable to the scope of the bidding package. + Part 3.2.