Construction and equipment installation

Tender ID
Views
8
Contractor selection plan ID
Bidding package name
Construction and equipment installation
Bidding method
Online bidding
Tender value
3.317.592.000 VND
Publication date
10:19 10/09/2025
Contract Type
All in One
Domestic/ International
Domestic
Contractor Selection Method
Single Stage Single Envelope
Fields
Constructions
Approval ID
Số 15/QĐ-TTHĐTTN
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Decision-making agency
Children's house in Quang Tri province
Approval date
10/09/2025
Tendering result
There is a winning contractor
List of successful bidders
Number Business Registration ID ( on new Public Procuring System) Consortium Name Contractor's name Bid price Technical score Winning price Delivery time (days) Contract date
1 vn3200489457

TRUONG THUAN TIEN COMPANY LIMITED

2.664.689.791,5904 VND 2.664.690.000 VND 150 day
List of unsuccessful bidders:
Number Business Registration ID ( on new Public Procuring System) Consortium Name Contractor's name Reason for failure
1 vn3200699373 Liên danh Nhà Thiếu nhi tỉnh Quảng Trị TTP JOINT STOCK COMPANY Including 2 contractors: TTP Joint Stock Company and Trong Tin Company: * About construction equipment: - Air compressor ≥360m3/h (01 machine): The contractor declares on webfom 01 machine, owned, attached with invoices to prove ownership but no registration/testing certificate is still valid as required by E-HSMT. Accordingly, on August 5, 2025, the bid solicitor issued Official Letter No. 22-CV/NTN asking the contractor to clarify E-HSDT the construction package for construction and installation of equipment of the project: Repairing and renovating children's houses in Quang Tri province. However, by the end of the clarification time, the contractor did not have a written response. Hence the contractor's E-HSDT is assessed to not achieve capacity and experience
2 vn3200662655 DUC MANH QUANG TRI COMPANY LIMITED * Competence and experience: Criteria "Experience in implementing similar construction contracts": At the request of E-HSMT, the provisions of "from January 1, 2022 to the time of bid closure, the contractor has completed all or completed the majority of the minimum of 02 works: The type of structure: Civil works, granted: III In which at least one work value is 1,660,000,000 VND and the total value of all the main constructions is 3.320,000 VND. Members of the joint venture), the manager or subcontractor in which x = 2 x V. In case the contractor has completed all or most of the project to meet the requirements of the type of structure, the work level and a value of ≥ x, it is considered as a response ”. At E-HSDT of the contractor: The contractor has declared the implementation of the construction contract: Trieu Van Kindergarten; Category: 2 -storey house 6 classrooms. Attach the contract, the dossier of payment of the 3rd construction and installation volume, the acceptance record completed to prove. However, there is a lack of documents proving the type and construction level at the request of E-HSMT. * The technical capacity: About construction equipment: - Air compressor ≥360m3/h (1 machine): The contractor declares on webfom 01 machine (rented), enclosed with the principle contract to hire construction equipment, but the attached document is a pressure bottle, not an air compressor so it does not meet the requirements of E-HSMT. Accordingly, on August 5, 2025, the bid solicitor issued Official Letter No. 19-CV/NTN asking the contractor to clarify E-HSDT the construction package for construction and installation of equipment under the work: Repairing and renovating children's houses in Quang Tri province. However, by the end of the clarification time, the contractor did not have a written response. Hence the contractor's E-HSDT is assessed to not achieve capacity and experience
3 vn3200598738 CÔNG TY TRÁCH NHIỆM HỮU HẠN MỘT THÀNH VIÊN TIẾN QUÂN PHÚ * About construction equipment: - Air compressor ≥360m3/h (1 machine): Contractor declares on webfom 01 machine (owned), accompanied by invoices, but lack of test paper as required by E-HSMT. Accordingly, on August 5, 2025, the bid solicitor issued Official Letter No. 24-CV/NTN asking the contractor to clarify E-HSDT the construction package for construction and installation of equipment of the project: Repairing and renovating children's houses in Quang Tri province. On August 10, 2025, the contractor issued an additional dispatch and clarified E-HSDT number No. 03/2025/LR-TQP. However, in the official dispatch, the contractor did not provide documents proving to meet the requirements of E-HSMT. Hence the contractor's E-HSDT is assessed to not achieve capacity and experience
4 vn3200667438 Nhà Thiếu nhi tỉnh Quảng Trị CÔNG TY TRÁCH NHIỆM HỮU HẠN MỘT THÀNH VIÊN XÂY DỰNG VÀ THƯƠNG MẠI ALPHA QUẢNG TRỊ * About construction equipment: - Air compressor ≥360m3/h (01 machine): The contractor declares on webfom 01 machine, owned, attached with invoices to prove ownership but no registration/testing certificate is still valid as required by E-HSMT. Accordingly, on August 5, 2025, the bid solicitor issued Official Letter No. 22-CV/NTN asking the contractor to clarify E-HSDT the construction package for construction and installation of equipment of the project: Repairing and renovating children's houses in Quang Tri province. However, by the end of the clarification time, the contractor did not have a written response. Hence the contractor's E-HSDT is assessed to not achieve capacity and experience
5 vn3200484508 Liên danh sửa chữa, cải tạo Nhà Thiếu nhi tỉnh Quảng Trị TINH NHU PHAT COMPANY LIMITED * Regarding key personnel: - The position of the commander of the construction site: The contractor proposed that Mr. Nguyen Dang Cuong, with a qualification; Certificate of supervision of construction of civil - industrial works and confirmation of the investor on the experience of participating in the commander of the repair work of the room, the lecture hall for the practice room of Quang Tri Medical College (in the Certificate of no information and construction level). Lack of citizen identification; Certificate of occupational safety and hygiene is still at least until the time of bid opening and the commitment of personnel with the contractor on participating in the implementation of the bidding package. In addition, the contractor declares personnel to participate in the commander of the works: (1) Bidding package for repairing and repairing classrooms, lecture halls in Quang Tri Medical College. (2) Bidding package: New paint of theoretical and practical house in Quang Tri Te College. (3) Construction and repair of Gio My High School and Secondary School, item: Thuong My cluster, central school. (4) Bidding package for repairing fences, office houses, 2 -storey school houses, semi -boarding houses and security schools in Quang Tri province with disabilities. However, E-HSDT does not attach documents to prove personnel participating in works (2), (3) and (4) to meet the requirements. - Technical location for construction of civil items: The contractor proposes to be Mr. Ho Thanh Viet, with a qualification and confirmation of the investor to prove the experience. E-HSDT has not attached citizen identification and commitment of personnel with the contractor about participating in the implementation of the bidding package. - Technical location for construction of electrical systems: The contractor proposes to be Mr. Tran Quang Tan, with a qualification and confirmation of the investor to prove the experience. E-HSDT has not attached citizen identification and commitment of personnel with the contractor about participating in the implementation of the bidding package.
6 vn3200643109 Liên danh sửa chữa, cải tạo Nhà Thiếu nhi tỉnh Quảng Trị CÔNG TY TRÁCH NHIỆM HỮU HẠN XE BUS QUẢNG TRỊ * Regarding key personnel: - The position of the commander of the construction site: The contractor proposed that Mr. Nguyen Dang Cuong, with a qualification; Certificate of supervision of construction of civil - industrial works and confirmation of the investor on the experience of participating in the commander of the repair work of the room, the lecture hall for the practice room of Quang Tri Medical College (in the Certificate of no information and construction level). Lack of citizen identification; Certificate of occupational safety and hygiene is still at least until the time of bid opening and the commitment of personnel with the contractor on participating in the implementation of the bidding package. In addition, the contractor declares personnel to participate in the commander of the works: (1) Bidding package for repairing and repairing classrooms, lecture halls in Quang Tri Medical College. (2) Bidding package: New paint of theoretical and practical house in Quang Tri Te College. (3) Construction and repair of Gio My High School and Secondary School, item: Thuong My cluster, central school. (4) Bidding package for repairing fences, office houses, 2 -storey school houses, semi -boarding houses and security schools in Quang Tri province with disabilities. However, E-HSDT does not attach documents to prove personnel participating in works (2), (3) and (4) to meet the requirements. - Technical location for construction of civil items: The contractor proposes to be Mr. Ho Thanh Viet, with a qualification and confirmation of the investor to prove the experience. E-HSDT has not attached citizen identification and commitment of personnel with the contractor about participating in the implementation of the bidding package. - Technical location for construction of electrical systems: The contractor proposes to be Mr. Tran Quang Tan, with a qualification and confirmation of the investor to prove the experience. E-HSDT has not attached citizen identification and commitment of personnel with the contractor about participating in the implementation of the bidding package.
7 vn3200147580 Liên danh Nhà Thiếu nhi tỉnh Quảng Trị CÔNG TY TRÁCH NHIỆM HỮU HẠN TRỌNG TÍN Including 2 contractors: TTP Joint Stock Company and Trong Tin Company: * About construction equipment: - Air compressor ≥360m3/h (01 machine): The contractor declares on webfom 01 machine, owned, attached with invoices to prove ownership but no registration/testing certificate is still valid as required by E-HSMT. Accordingly, on August 5, 2025, the bid solicitor issued Official Letter No. 22-CV/NTN asking the contractor to clarify E-HSDT the construction package for construction and installation of equipment of the project: Repairing and renovating children's houses in Quang Tri province. However, by the end of the clarification time, the contractor did not have a written response. Hence the contractor's E-HSDT is assessed to not achieve capacity and experience
8 vn3200610311 Nhà Thiếu nhi tỉnh Quảng Trị CÔNG TY TRÁCH NHIỆM HỮU HẠN MỘT THÀNH VIÊN CHÂU LONG QUẢNG TRỊ * About construction equipment: - Air compressor ≥360m3/h (01 machine): The contractor declares on webfom 01 machine, owned, attached with invoices to prove ownership but no registration/testing certificate is still valid as required by E-HSMT. Accordingly, on August 5, 2025, the bid solicitor issued Official Letter No. 22-CV/NTN asking the contractor to clarify E-HSDT the construction package for construction and installation of equipment of the project: Repairing and renovating children's houses in Quang Tri province. However, by the end of the clarification time, the contractor did not have a written response. Hence the contractor's E-HSDT is assessed to not achieve capacity and experience