TN-01: Static pile compression test

Tender ID
Views
3
Contractor selection plan ID
Bidding package name
TN-01: Static pile compression test
Bidding method
Online bidding
Tender value
977.194.183 VND
Estimated price
925.203.596 VND
Publication date
09:31 28/03/2025
Contract Type
All in One
Domestic/ International
Domestic
Contractor Selection Method
Single Stage Two Envelopes
Fields
Consulting
Approval ID
KQ2500037433_2503280852
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Decision-making agency
Endocrine central hospital
Approval date
28/03/2025
Tendering result
There is a winning contractor
List of successful bidders
Number Business Registration ID ( on new Public Procuring System) Consortium Name Contractor's name Bid price Technical score Winning price Delivery time (days) Contract date
1 vn0102131178

CONSTRUCTION SURVEY AND CONSULTANCY VERIFY JOINT STOCK COMPANY

919.399.400 VND 91 919.399.400 VND 25 day
List of unsuccessful bidders:
Number Business Registration ID ( on new Public Procuring System) Consortium Name Contractor's name Reason for failure
1 vn0101439259 HANOI CONSTRUCTION DESIGN INVESTGATION CONSULTANTS JOINT STOCK COMPANY Regarding the standard "Solutions and methodology" in Section 3 of Chapter III of E-HSMT: The total evaluation score on criteria on the contractor reaches 14.5/35 points lower than the minimum point is considered to meet the requirements of "solutions and methodology" (28 points)