DauThau.info discovered that this project's data collected from the new National Bidding Network System has differences in the investor compared to the data on the old system as follows:
⚬ New system: THE NORTHERN VIET NAM POWER PROJECTS MANAGEMENT BOARD-BRANCH OF NATIONAL POWER TRANSMISSION CORPORATION
⚬ Old system: National Power Transmission Corporation
In addition, the bidding information related to this project also has discrepancies regarding the investor, specifically:
- The following contractor selection plans have the investor THE NORTHERN VIET NAM POWER PROJECTS MANAGEMENT BOARD-BRANCH OF NATIONAL POWER TRANSMISSION CORPORATION:
⚬ Installing the 2nd transformer Ba Thien 220 kV substation
- The following contractor selection plans have the investor NATIONAL POWER TRANSMISSION CORPORATION:
⚬ Adjustment of the second phase of the LC (package 7)-the project of Installing the second transformer, Ba Thien 220kV substation
⚬ Installing the 2nd transformer Ba Thien 220 kV substation
- The following contractor selection plans have the investor National Power Transmission Corporation:
⚬ KHLCNT phase 2 (bid package No. 6) - project Installing the second transformer at Ba Thien 220kV transformer station
- The following bidding packages have the investor NATIONAL POWER TRANSMISSION CORPORATION:
⚬ Package 10: Construction supervision consultancy and equipment installation
⚬ Package 07: Supply and transport the second VTTB (including station control system; Camera)
⚬ Package No. 5: Supply and transport transformer 220 kV - 250 MVA
⚬ Package No. 06: Supply and transportation of the first VTTB
- The following bidding packages have the investor The Northern Power Viet Nam Projects Management Board:
⚬ Package No. 1: Providing consulting services for preparation of technical reports
⚬ Package No. 2: Providing consulting services for verification of TKCS
⚬ Package No. 11: Construction insurance
⚬ Package No. 8: Construction and installation of substations
Contractor selection plans for this project
NO | Contractor selection plan ID | Contractor selection plan name | Total investment |
---|---|---|---|
1
|
659.760.000 VND |
||
2
|
69.698.000.000 VND |
||
3
|
69.698.000.000 VND |
||
4
|
69.698.000.000 VND |
||
Total amount |
209.753.760.000 VND |
Statistical table of bidding packages under the project
Statistics by type of bidding package | Statistics by form | Online bidding value (billion VND) | Number of bidding packages whose results have been posted | |||||
---|---|---|---|---|---|---|---|---|
Goods | Civil Works | Consulting | Other categories | Non-Consulting | Online | Offline | ||
5 | 1 | 0 | 0 | 1 | 9 | 2 | 82.37 | 8 |