Preventing overload of substations in Thanh Hoa province

Watching          
Found: 14:19 22/11/2022
Project number
PR2200026243-00
Notice type
Real announcement
Project name
Preventing overload of substations in Thanh Hoa province
Project objective
- Anti-overload, reduce power loss. - Overcoming the current overload situation and in the coming years. - Increase the amount of commercial electricity, expand the business capacity of Thanh Hoa Power Company in the project area. - Improve reliability, ensure power quality standards for electricity users and improve MAIFI, SAIFI, SAIDI power supply indexes.
Investor ID
vnz000018174
Authority
Northern Power Corporation
Project duration
70 Day
Project Category
Group C
Project management Type
Another form
Use of ODA funds
No
Implementation location
Thành phố Thanh Hoá, Thanh Hoá
Investment Total Value
To view full information please Login or Register
Project approval ID
1669/QĐ-EVNNPC ngày 19/7/2022
Project approval date
18/07/2022
Approval authority
Tổng Công ty Điện lực miền Bắc
Approval documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611

Contractor selection plans for this project

NO Contractor selection plan ID Contractor selection plan name Total investment
1
14.912.000.000 VND
Total amount
14.912.000.000 VND

Statistical table of bidding packages under the project

Statistics by type of bidding package Statistics by form Online bidding value (billion VND) Number of bidding packages whose results have been posted
Goods Civil Works Consulting Other categories Non-Consulting Online Offline
0 0 1 0 0 1 0 0.07 1