Tay Ninh 1 500 kV transformer station and connection lines
Project number
PR2400070995-00
Notice type
Real announcement
Project name
Tay Ninh 1 500 kV transformer station and connection lines
Project objective
Ensuring power supply for loads and meeting the economic and social development needs of Tay Ninh province and neighboring provinces and cities (Ho Chi Minh City, Binh Duong).
Reduce load for 500/220 kV transformers (MBA) at the existing/under-construction 500 kV Cu Chi, Cau Bong, Duc Hoa, Chon Thanh transformer stations and existing 220 kV lines in the area.
Contribute to ensuring N-1 criteria, enhancing power system stability, improving reliability and safety of power supply for the National power system and relieving work
Authority
Nguyen Tuan Tung
Project duration
2026 Year
Project management Type
The investor directly manages the project
Project approval ID
170/QĐ-HĐTV
Project approval date
18/09/2024
Approval authority
TỔNG CÔNG TY TRUYỀN TẢI ĐIỆN QUỐC GIA
Approval documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register
3. QDPD FS TBA 500kV Tay Ninh 1 va dau noi (f).pdf
Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Contractor selection plans for this project
| NO |
Contractor selection plan ID |
Contractor selection plan name |
Total investment |
|
1
|
|
2.050.358.000.000 VND |
Total amount |
2.050.358.000.000 VND |
Statistical table of bidding packages under the project
| Statistics by type of bidding package |
Statistics by form |
Online bidding value (billion VND) |
Number of bidding packages whose results have been posted |
| Goods |
Civil Works |
Consulting |
Other categories |
Non-Consulting |
Online |
Offline |
| 0 |
0 |
2 |
0 |
1 |
3
|
0 |
40.58
|
3
|