Status
Tender opening completed
Bidding package name
Bidding package: Construction costs
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Upgrading the asphalt carpet of Ut Cuu road, the remaining section and Ut Me - Tan Hoa (section from Luc Vien road - KT11 canal)
Contract execution period
180 day
Contractor selection methods
Competitive Offer
Award date
07:00 05/04/2024
Bid opening completion time
10:46 05/04/2024
Total Number of Bidders
3
Technical Evaluation
Number Right Scoring (NR)