Status
Tender opening completed
Bidding package name
Civil Works
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
KHLCNT- Repairing Viet Doan Kindergarten, Tien Du district; Items: Repairing schools in Long Kham, Long Van, Cho Son, Dai Tao, Lien Ap villages
Contract execution period
60 day
Contractor selection methods
Competitive Bidding
Award date
18:30 09/09/2023
Bid opening completion time
20:22 09/09/2023
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)