Status
Tender opening completed
Bidding package name
Construction
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
The third floor of the two-story, six-classroom school building, along with the three-story foundation.
Contract execution period
60 day
Contractor selection methods
Competitive Offer
Award date
15:00 24/02/2023
Bid opening completion time
15:01 24/02/2023
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)