Status
Tender opening completed
Bidding package name
Construction
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Repairing and overcoming erosion prevention embankments on the village axis concrete road in group 5 of Phuoc Thanh village
Contract execution period
75 day
Contractor selection methods
Competitive Bidding
Award date
07:00 08/12/2024
Bid opening completion time
07:01 08/12/2024
Total Number of Bidders
3
Technical Evaluation
Number Right Scoring (NR)