Status
Tender opening completed
Bidding package name
Package 01: Construction and installation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Plan for selecting a contractor to implement the project: Construction of a road encircling the residential area of Nghia Lai village, Uy No ward, according to the approved plan.
Contract execution period
540 day
Contractor selection methods
Competitive Bidding
Contract Type
According to the adjusted unit price
Award date
14:30 05/09/2026
Bid opening completion time
14:40 05/09/2026
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
View by batch