Status
Tender opening completed
Bidding package name
Package 01. Construction of works
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Adjust the plan to select the contractor to repair the damage of the background, road and construction on the line of Km0-Km0+800, Km50+200-Km51+400, Vinh Tuy-Yen Binh Street (DT.183)
Contract execution period
150 day
Contractor selection methods
Competitive Bidding
Contract Type
According to fixed unit price
Award date
08:00 12/05/2025
Bid opening completion time
08:00 12/05/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
8.784.718.192 VND
View by batch