Status
Tender opening completed
Bidding package name
Package 02: construction work
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Repairing and overcoming consequences after storm No. 3 at Dai Ban Commune People's Committee Office
Contract execution period
40 day
Contractor selection methods
Competitive Bidding
Award date
10:00 16/12/2024
Bid opening completion time
11:14 16/12/2024
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)