Status
Completing bid evaluation
Bidding package name
Package 04 – Construction supervision consultancy
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Plan to select the remaining bidding packages
Contract execution period
180 day
Contractor selection methods
Competitive Bidding
Award date
14:30 06/04/2023
Bid opening completion time
14:32 06/04/2023
Total Number of Bidders
3
Technical Evaluation
Number Right Scoring (NR)