Status
Tender opening completed
Bidding package name
Package 07: Entire part of construction work
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Renovating and expanding the main road of Van Khe commune, Me Linh district (along the route of Khe Ngoai 3 village, Khe Ngoan 4)
Contract execution period
210 day
Contractor selection methods
Competitive Bidding
Award date
10:00 30/06/2025
Bid opening completion time
11:04 30/06/2025
Total Number of Bidders
2
Technical Evaluation
Number Right Scoring (NR)