Status
Complete opening of financial documents
Bidding package name
Package 12: Audit of completed project settlement reports
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
KHLCNT phase 5 - 220kV transformer station of Nghi Son Economic Zone and connection line
Contract execution period
60 day
Contractor selection methods
Competitive Bidding
Award date
09:00 03/06/2025
Bid opening completion time
09:04 03/06/2025
Total Number of Bidders
3
Technical Evaluation
Number Right Scoring (NR)
Estimated price
1.076.908.000 VND