Status
Tender opening completed
Bidding package name
Package 5: Construction insurance
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Complete protection system, Scada/HMI computer system and E1.15, E1.16 and E1.22 station telecommunications system
Contract execution period
210 day
Contractor selection methods
Shortened competitive offer
Award date
14:00 19/10/2022
Bid opening completion time
14:09 19/10/2022
Total Number of Bidders
3
Technical Evaluation
Number Right Scoring (NR)
Estimated price
29.224.974 VND