Status
Tender opening completed
Bidding package name
Tender package No 03: Construction and installation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Plan for selecting contractors for project investment packages under the project: Upgrading main roads and group 2 roads in Vinh Lap area
Contract execution period
150 day
Contractor selection methods
Competitive Offer
Contract Type
According to fixed unit price
Award date
10:00 25/07/2026
Bid opening completion time
10:04 25/07/2026
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)