Status
Tender opening completed
Bidding package name
Tender package No 04: Construction part
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Long Hoa flood drainage ditch (phase 2), Hung Dong commune
Contract execution period
6 day
Contractor selection methods
Competitive Bidding
Award date
08:00 11/04/2024
Bid opening completion time
08:49 11/04/2024
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)