Status
Tender opening completed
Bidding package name
Tender package No 05: Construction and installation
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Solidifying KTB2 canal in Vu Ban commune, Binh Luc district
Contract execution period
270 day
Contractor selection methods
Competitive Bidding
Award date
08:00 24/01/2025
Bid opening completion time
08:59 24/01/2025
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)