Tender package No 21: Construction supervision consultancy

      Watching  
Tender ID
Status
Complete opening of financial documents
Bidding package name
Tender package No 21: Construction supervision consultancy
Fields
Tư vấn
Bidding method
Online
Awarded at
Website: http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Adjustment of the 3rd phase (Package No. 14) - Project: 220 kV Sam Son transformer station and 220 kV Thanh Hoa - Sam Son connection line
Contract execution period
365 day
Contractor selection methods
Competitive Bidding
Contract Type
All in one
Award date
09:00 01/12/2024
Bid opening completion time
09:26 01/12/2024
Tender value
To view full information, please Login or Register
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)
Estimated price
9.671.095.000 VND
Information of participating contractors:
Total Number of Bidders: 1
Business Registration ID ( on new Public Procuring System)
vn0100878648
Province/City
Hà Nội
Bid price
To view full information, please Login or Register
Discount rate (%)
0
Bid price after discount (if applicable) (VND)
To view full information, please Login or Register
Price Review
To view full information, please Login or Register
Technical score
92
Price point
0
Bid security value (VND)
To view full information, please Login or Register
Validity of Bid Security
0 day
E-Bid validity (date)
150 day
Bid join time
The system analyzed and found the following joint venture contractors:
Views: 3
You did not use the site, Click here to remain logged. Timeout: 60 second