Status
Tender opening completed
Bidding package name
Tender package No 05: Construction work
Awarded at
Website:
http://muasamcong.mpi.gov.vn
Bidding Procedure
Single Stage Single Envelope
Contractor Selection Plan ID
Contractor Selection Plan Name
Contractor selection plan for bidding packages of the project: Construction of Dong Ngoai bridge, Phong Lam 3 village, Nam Thuy Anh commune
Contract execution period
150 day
Contractor selection methods
Competitive Bidding
Contract Type
According to fixed unit price
Award date
09:00 08/07/2026
Bid opening completion time
09:19 08/07/2026
Total Number of Bidders
1
Technical Evaluation
Number Right Scoring (NR)