Bidder Selection Plan

Adjusting and supplementing the plan to select contractors of dredging, improving the environment, construction of Xuyen Tam canal infrastructure (from Nhieu Loc - Thi Nghe canal to Vam Thuat River) in Binh Thanh District, Go Vap District

  Watching      
Find: 16:49 29/08/2025
Contractor Selection Plan ID
PL2500145358-03
Publishing time
16:44 29/08/2025
Posting Status
Published
Contractor selection plan name
Adjusting and supplementing the plan to select contractors of dredging, improving the environment, construction of Xuyen Tam canal infrastructure (from Nhieu Loc - Thi Nghe canal to Vam Thuat River) in Binh Thanh District, Go Vap District
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500036159-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group A
Project implementation time
6 Years
Authority that issues the decision
Ban Quản lý dự án đầu tư xây dựng hạ tầng đô thị Thành phố Hồ Chí Minh
Approval date
11/08/2025
Approval ID
384/QĐ-BHTĐT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Decision-making agency, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 13
1.TV-12 bidding package: Construction supervision consultant for construction package XL-01
Tender/ Prequalification Notice ID
Contract execution period
960 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision of construction package XL-01
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.TV-13 bidding package: Supervision consultancy on construction of XL-02 bidding package
Tender/ Prequalification Notice ID
Contract execution period
960 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision of construction package XL-02
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.TV-15 bidding package: Completed project audit consultancy
Tender/ Prequalification Notice ID
Contract execution period
515 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Completed project audit consulting
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter IV, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.PTV-01 Package: Construction insurance for the XL-01 bidding package
Tender/ Prequalification Notice ID
Contract execution period
960 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance for the XL-01 bidding package
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Bidding Package PTV-02: Insurance for construction of Bidding Package XL-02
Tender/ Prequalification Notice ID
Contract execution period
960 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance for XL-02 bidding package
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
6.Package XL -01: section from Nhieu Loc - Thi Nghe canal to Bui Dinh Tuy Bridge, including Cau Son canal (from km0+000 to km2+512)
Tender/ Prequalification Notice ID
Contract execution period
960 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of section from Nhieu Loc - Thi Nghe canal to Bui Dinh Tuy Bridge, including Cau Son Rach (from Km0+000 to Km2+512)
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
7.Package XL-02: The section from Bui Dinh Tuy Bridge to Luong Ngoc Quyen Street, including Rach Binh Loi, Rach Binh Trieu (from Km2+512 to Km5+216)
Tender/ Prequalification Notice ID
Contract execution period
960 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of section from Bui Dinh Tuy Bridge to Luong Ngoc Quyen Street, including Rach Binh Loi, Rach Binh Trieu (from Km2+512 to Km5+216)
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
8.TV-18 bidding package: Consulting required records and evaluation of bidding proposals: Power grid relocation
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare required records and evaluate the dossier of proposal package: Memitating the grid
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
9.TV-19 bidding package: Consulting on supervision of construction of electricity grids
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction of electricity grids
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
10.Bidding package: relocate the power grid
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of the grid relocated is affected within the project scope
Capital source details
city budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
11.TV-20 bidding package: Consulting, verifying new norms, adjustment norms
Tender/ Prequalification Notice ID
Contract execution period
1050 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting to determine, verify new norms, adjustment norms
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP.Hồ Chí Minh
12.TV-21 Package: Consulting for making bidding documents and evaluating bidding documents TV-09, TV-12, TV-13, TV-15, PTV-01, PTV-02, XL-01, XL-02
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting to compile bidding documents and evaluate bidding documents TV-09, TV-12, TV-13, TV-15, PTV-01, PTV-02, XL-01, XL-02
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
13.TV-09 bidding package: Environmental monitoring and supervision consultant
Tender/ Prequalification Notice ID
Contract execution period
960 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Environmental monitoring and monitoring during the construction process
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Adjusting and supplementing the plan to select contractors of dredging, improving the environment, construction of Xuyen Tam canal infrastructure (from Nhieu Loc - Thi Nghe canal to Vam Thuat River) in Binh Thanh District, Go Vap District". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Adjusting and supplementing the plan to select contractors of dredging, improving the environment, construction of Xuyen Tam canal infrastructure (from Nhieu Loc - Thi Nghe canal to Vam Thuat River) in Binh Thanh District, Go Vap District" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 24

You did not use the site, Click here to remain logged. Timeout: 60 second