Bidder Selection Plan

Approval of project plan: Installing T2 transformer of Cat Hai 110kV substation, under the Program to support the development of policy reform of the electricity sector - phase 3 - DPL3

  Watching    
Project Contractor selection plan Tender notice Bid award
Find: 16:29 20/11/2018
Contractor selection plan ID
20181149252-00
Publication date
16:29 20/11/2018
Publication status
Actual notification
Contractor selection plan name
Approval of project plan: Installing T2 transformer of Cat Hai 110kV substation, under the Program to support the development of policy reform of the electricity sector - phase 3 - DPL3
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20181149147-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
19/11/2018
Approval ID
4324/QĐ-BCT
Related announcements

- Change: Notification form, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 6
1.Package 04: Supply and delivery of 110kV MBA MBA
Tender/ Prequalification Notice ID
Contract Period
150 days
Domestic/ International
International
Bidding method
Directly
Fields
Goods
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
DPL3
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2018
Contract Type
All in one
Prequalification
No
Location
2.Package 05: Supplying 110kV VTTB, supplying and installing information systems, SCADA and 110kV substation construction
Tender/ Prequalification Notice ID
Contract Period
150 days
Domestic/ International
International
Bidding method
Directly
Fields
Mixture
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
DPL3
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
November 2018
Contract Type
According to fixed unit price
Prequalification
No
Location
3.Package 06: Testing for calibration of 110kV . substation
Tender/ Prequalification Notice ID
Contract Period
30 days
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
EVNNPC
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
December 2018
Contract Type
All in one
Prequalification
No
Location
4.Tender package No 07: Construction insurance
Tender/ Prequalification Notice ID
Contract Period
Follow the Day
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
EVNNPC
Contractor Selection Type
Offers are competitive, domestic, not pre-qualified, not online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
December 2018
Contract Type
All in one
Prequalification
No
Location
5.Tender package No 08: Construction audit
Tender/ Prequalification Notice ID
Contract Period
30 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
EVNNPC
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March 2019
Contract Type
All in one
Prequalification
No
Location
6.Package 09: Supervision of construction and equipment installation
Tender/ Prequalification Notice ID
Contract Period
Follow the Day
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
EVNNPC
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
December 2018
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Approval of project plan: Installing T2 transformer of Cat Hai 110kV substation, under the Program to support the development of policy reform of the electricity sector - phase 3 - DPL3". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Approval of project plan: Installing T2 transformer of Cat Hai 110kV substation, under the Program to support the development of policy reform of the electricity sector - phase 3 - DPL3" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.