Bidder Selection Plan
BIDDING PLAN INVESTMENT STAGE
Contractor selection plan ID
20181115373-00
Publication date
10:13 13/11/2018
Publication status
Actual notification
Contractor selection plan name
BIDDING PLAN INVESTMENT STAGE
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20181074168-00
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Approval ID
266/QĐ-TANDTC-KHTC
List of Bid:
Number of packages: 13
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
2. Supply and installation of equipment
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
3. Prepare bidding documents, PTDG, construction bidding documents
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
4. Prepare bidding documents for PTDG bidding documents for equipment supply and installation
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
5. Prepare bidding documents PTDG construction supervision bidding documents
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
6. Evaluation of bidding documents, results of evaluation of bids for construction bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
7. Evaluation of bidding documents, results of evaluation of bidding packages for equipment supply and installation
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
8. Evaluation of bidding documents, results of evaluation of bids for construction and installation bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
9. Construction supervision
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
10. Equipment installation supervision
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
11. make a commitment to protect the environment
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2018
12. Construction insurance
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
13. Evaluation of bidding documents, results of evaluation of bids for construction supervision bidding package
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Government budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2018
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "BIDDING PLAN INVESTMENT STAGE". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email