Bidder Selection Plan

Contractor selection plan for the Project Preparation phase, under the project: Replacing distribution transformers that have been operating for over 25 years in Hung Yen province

  Watching      
Find: 12:48 07/11/2023
Contractor Selection Plan ID
PL2300212709-00
Publishing time
08:38 07/11/2023
Posting Status
Published
Contractor selection plan name
Contractor selection plan for the Project Preparation phase, under the project: Replacing distribution transformers that have been operating for over 25 years in Hung Yen province
Investment objective
Reducing incidents, reducing power loss on the grid, contributing to improving power quality and reliability of power supply in Hung Yen province.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300051340-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
1 Years
Location
Hung Yen province
Authority that issues the decision
Công ty Điện lực Hưng Yên - Chi nhánh Tổng công ty Điện lực miền Bắc
Approval date
07/11/2023
Approval ID
3282/QĐ-PCHY
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Package 02 – Purchase of transformers
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial credit capital of the Northern Power Corporation
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
2.Package 03 – Construction and procurement of remaining materials
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial credit capital of Northern Power Corporation
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
3.Package 04 – Construction supervision consulting
Tender/ Prequalification Notice ID
Contract execution period
45 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Basic Depreciation Capital of Northern Power Corporation
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
4.Package 05 – Construction audit
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Basic Depreciation Capital of Northern Power Corporation
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for the Project Preparation phase, under the project: Replacing distribution transformers that have been operating for over 25 years in Hung Yen province". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for the Project Preparation phase, under the project: Replacing distribution transformers that have been operating for over 25 years in Hung Yen province" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 5

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8493 Projects are waiting for contractors
  • 1035 Tender notices posted in the last 24 hours
  • 1293 Contractor selection plan posted in the last 24 hours
  • 25334 Tender notices posted in the past month
  • 39392 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second