Bidder Selection Plan

Contractor selection plan for Vo Nguyen Giap road construction investment project (section from Lien Hong intersection to Hanoi - Hai Phong expressway intersection)

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 22:33 13/12/2025
Contractor Selection Plan ID
PL2500342792-00
Publishing time
22:32 13/12/2025
Posting Status
Published
Contractor selection plan name
Contractor selection plan for Vo Nguyen Giap road construction investment project (section from Lien Hong intersection to Hanoi - Hai Phong expressway intersection)
Investment objective
Investing in the construction of Vo Nguyen Giap road (section from Lien Hong intersection to Hanoi - Hai Phong expressway intersection) to gradually improve regional transport infrastructure according to planning; ensure safe circulation, improve traffic capacity on the route, promote the effectiveness of the traffic axis connecting with Hanoi - Hai Phong expressway and National Highway 5; create motivation for regional socio-economic development.
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500069006-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
2 Years
Authority that issues the decision
Ban Quản lý dự án đầu tư xây dựng Tây Hải Phòng
Approval date
09/12/2025
Approval ID
2419/QĐ-BQLDA
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 10
1.Package 01: Survey, design construction drawings and cost estimates
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Survey, Design construction drawings and cost estimates
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
December 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Package 02: Verification of construction drawing design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verify construction drawing designs and estimates, and verify traffic safety at the design step of physical protection
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
December 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.Tender package No 03: Survey, plan and estimate clearance of bombs, mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Surveying, planning and estimates of mine clearance and explosive objects
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
December 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Package 04: Clearing mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Clearing mine, explosive objects
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Bidding package No. 05: Appraisal of prices of supplies, materials and equipment
Tender/ Prequalification Notice ID
Contract execution period
5 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Valuation of materials, materials, equipment
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
6.Tender package No 06: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Building insurance package 07
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter I, 2026
Type of contract
By percentage
Prequalification
No
Implementation location (After merge)
7.Tender package No 07: Construction work
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Civil Works
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
8.Package 08: Supervision of construction works
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction works
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
9.Package 09: Traffic safety verification before being put into use
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Traffic safety inspection before putting into use
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
10.Package 10: Audit of completed projects
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Completed project audit
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan for Vo Nguyen Giap road construction investment project (section from Lien Hong intersection to Hanoi - Hai Phong expressway intersection)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan for Vo Nguyen Giap road construction investment project (section from Lien Hong intersection to Hanoi - Hai Phong expressway intersection)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 4

You did not use the site, Click here to remain logged. Timeout: 60 second