Contractor Selection Plan ID
PL2400098435-00
Publishing time
08:58 04/06/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan (phase 2) Project: Renovating and upgrading canals and works on irrigation canal N3 section from K12+650 to K19+050
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Spending Category
Investment and Development Spending
Location
Authority that issues the decision
CÔNG TY TNHH MỘT THÀNH VIÊN KHAI THÁC CÔNG TRÌNH THỦY LỢI NAM SÔNG THƯƠNG
Approval date
30/05/2024
Approval ID
92/QĐ-NST
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Tender package No 01: Survey consultancy, preparation of economic and technical reports
Tender/ Prequalification Notice ID
Contract execution period
70 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Việt Yên District, Bắc Giang
2.Package 02: Consulting and monitoring survey
Tender/ Prequalification Notice ID
Contract execution period
35 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Việt Yên District, Bắc Giang
3.Tender package No 03: Consultancy and verification of design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Việt Yên District, Bắc Giang
4.Bidding package No. 04: Consulting on preparation of Bidding Documents, evaluation of Bidding Documents for survey consulting packages, preparation of Technical Audit Report
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Việt Yên District, Bắc Giang
5.Bidding package No. 05: Consulting on appraisal of environmental documents, LCNT results of survey consulting bidding package, preparation of Technical Audit Report
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Việt Yên District, Bắc Giang

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (phase 2) Project: Renovating and upgrading canals and works on irrigation canal N3 section from K12+650 to K19+050". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (phase 2) Project: Renovating and upgrading canals and works on irrigation canal N3 section from K12+650 to K19+050" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 3

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8522 Projects are waiting for contractors
  • 142 Tender notices posted in the last 24 hours
  • 158 Contractor selection plan posted in the last 24 hours
  • 23701 Tender notices posted in the past month
  • 37149 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second