Bidder Selection Plan

Contractor selection plan - Project: Supplementing and perfecting the protection function and transmission channel of transformer stations and 220kV lines

  Watching      
Find: 15:28 14/11/2025
Contractor Selection Plan ID
PL2300212240-04
Publishing time
15:23 14/11/2025
Posting Status
Published
Contractor selection plan name
Contractor selection plan - Project: Supplementing and perfecting the protection function and transmission channel of transformer stations and 220kV lines
Investment objective
- Provide parallel and independent transmission channels (independent of equipment, independently of the route) for the protective relay system. - Establish a transmission channel (F85) for 220 kV lines, thereby increasing safety for 220 kV lines. - Fully equipped the protection functions for the protective relay system of the contact compartment to meet the management of safe grid operation.
Project management forms
Another form
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300055233-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Authority that issues the decision
Tổng Công ty Truyền tải điện Quốc gia
Approval date
04/11/2025
Approval ID
2190/QĐ-EVNNPT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Investor, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Filter name, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Total investment, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 7
1.Package 3: Supply, install control systems, protection and information systems; Experimental correction experiments, SCADA systems and information systems
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and install control systems, protection and information systems; Experimental correction experiments, SCADA systems and information systems
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Đồng Nai
2.Package 4.1: Electrical calibration experiment (Pleiku 2 500 kV substation, Phu My 220 kV substation, Thap Cham 220 kV substation, Duc Trong 220 kV substation, Phan Thiet 220 kV substation, Ham Tan 220 kV substation)
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Electrical calibration experiment: 500 kV Pleiku 2 substation, 220 kV Phu My substation, 220 kV Thap Cham, 220 kV Duc Trong, 220 kV Phan Thiet, 220 kV Ham Tan
Capital source details
EVNNPT
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Bình Định
3.Package 5: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
940 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance for construction
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Cần Thơ
4.Package 6: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Consultancy and supervision of construction and installation
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Lâm Đồng
5.Package 7: Auditing the project settlement report completed
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit of completed project settlement reports
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hà Nội
6.Package 3.4: Supply and installation of DK-BV, TTLL-SCADA systems at 220kV substations Phu My, Binh Hoa, Cai Lay, Rach Gia 2, Long Binh, O Mon 2, Tra Noc 2, Chau Doc 2, Soc Trang 2
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
VTTB procurement includes installation and configuration services of MTMT, TTLL, SCADA at 220kV substations Phu My, Binh Hoa, Cai Lay, Rach Gia 2, Long Binh, O Mon 2, Tra Noc 2, Chau Doc 2, Soc Trang 2
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Gia Lai
7.Package 4.2: Electrical calibration experiment (220 kV Chau Doc 2 substation)
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Electrical calibration experiment: 220 kV Chau Doc 2 substation
Capital source details
EVNNPT
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Is different
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan - Project: Supplementing and perfecting the protection function and transmission channel of transformer stations and 220kV lines". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan - Project: Supplementing and perfecting the protection function and transmission channel of transformer stations and 220kV lines" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 6

You did not use the site, Click here to remain logged. Timeout: 60 second