Bidder Selection Plan

Contractor selection plan Project to build route DT.384B (section from the intersection with the road connecting the two expressways Hanoi - Hai Phong with Cau Gie - Ninh Binh expressway to the intersection with DT 378)

  Watching      
Find: 13:01 13/11/2024
Contractor Selection Plan ID
PL2400122346-01
Publishing time
08:32 13/11/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan Project to build route DT.384B (section from the intersection with the road connecting the two expressways Hanoi - Hai Phong with Cau Gie - Ninh Binh expressway to the intersection with DT 378)
Investment objective
Invest in road construction in order to complete the essential transport infrastructure system of the province, create favorable conditions for people's travel, and contribute to promoting socio-economic development in the districts: Yen My, Khoai Chau in particular and Hung Yen province in general
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300040856-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Authority that issues the decision
Uỷ ban nhân dân tỉnh Hưng Yên
Approval date
27/06/2024
Approval ID
1316/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Filter name, Investor, Approval date, Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 26
1.Bidding package No. 1: Preparation of E-Bidding Documents, evaluation of E-Bidding Documents for construction and relocation bidding packages of electrical works
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Select a construction unit to move electrical projects
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
2.Bidding package No. 2: Setting up the construction survey task for the Technical Protection Design step
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Set up tasks and update estimates for implementing the contract package of KS and BVTC preparation
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
3.Bidding package No. 3: Preparation of E-Bidding Documents and evaluation of E-Bidding Documents for the package of Consulting on surveying, preparing financial protection design and cost estimates
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Select an accounting consulting unit to prepare financial accounts-BVTC
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
4.Bidding package No. 4: Preparation of E-Bidding Documents and evaluation of E-Bidding Documents for construction bidding packages and ensuring traffic safety
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Select a construction unit to construct the project and ensure traffic safety
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
5.Bidding package No. 5: Prepare E-Bidding Documents and evaluate E-Bidding Documents for construction insurance bidding package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Choose a construction insurance service provider
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
6.Bidding package No. 6: Prepare E-HSMT and evaluate E-Bidding for site clearance pile installation bidding package
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Select a consulting unit to install site clearance stakes
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
7.Bidding package No. 7: Preparation of E-Bidding Documents and evaluation of E-Bidding Documents, consulting package for verifying financial protection accounts and estimates
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Select a consulting unit to verify TK-BVTC
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
8.Tender package No 8: Supervise the survey work of the design step of financial protection
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise the quality of inspection work to prepare financial accounts and financial statements
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
9.Tender package No 9: Supervision of construction works
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction quality
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
10.Tender package No 10: Supervision of site clearance deposit
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise the quality of site clearance pile installation work
Capital source details
Provincial budget
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Is different
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
11.Bidding package No. 11: Consulting on survey, design of physical protection and estimate of moving electrical works
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Select a consulting unit to design and move power lines
Capital source details
Provincial budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
12.Bidding package No. 12: Consulting on surveying, preparing financial protection design and estimates
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare TK-BVTC documents to serve construction works
Capital source details
Provincial budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
13.Bidding package No. 13: Consulting on verifying the design of financial protection and construction estimates
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Verify TK-BVTC documents according to current regulations
Capital source details
Provincial budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
14.Tender package No 14: Consulting on site clearance pile installation
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Install site clearance stakes to serve site clearance work
Capital source details
Provincial budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
15.Package 15: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
815 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance for construction incidents
Capital source details
Provincial budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
16.Tender package No 16: Construction and relocation of electrical works
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Select a power line moving unit to serve site clearance work
Capital source details
Provincial budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
17.Tender package No 17: Construction works and ensuring traffic safety
Tender/ Prequalification Notice ID
Contract execution period
380 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction works according to approved TK-BVTC documents
Capital source details
Provincial budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
18.Bidding package No. 18: Consulting on verifying the design of financial protection and estimating the relocation of electrical works
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Verify TK-BVTC documents for moving power lines according to current regulations
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
19.Tender package No 19: Consulting and supervision of construction and relocation of electrical works
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise the quality of power line construction works
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
20.Tender package No 20: Consulting on price appraisal to prepare construction estimates
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Unit price appraisal is not included in the price announcement
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
21.Tender package No 21: Insurance for construction and relocation of electrical works
Tender/ Prequalification Notice ID
Contract execution period
665 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance for construction incidents
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
22.Tender package No 22: Cost of energizing, accepting and handing over the line project
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Acceptance and trial run of the electrical system
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
23.Tender package No 23: Survey, estimate and construction of bomb, mine and explosive material clearance
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Uncategoried
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Carry out clearance of bombs, mines and explosives to serve construction work
Capital source details
Provincial budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
24.Tender package No 24: Supervising construction of bomb, mine and explosive material clearance
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise the quality of bomb, mine and explosive material clearance construction
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
25.Tender package No 25: Consulting on environmental monitoring and supervision
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Periodically check the impact of the project during construction on the surrounding environment
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province
26.Tender package No 26: Consulting on traffic safety verification before putting into use
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Check the traffic safety of the project according to current regulations before putting it into use
Capital source details
Provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Khoái Châu District, Hưng Yên
Implementation location (Before merge)
Hung Yen province

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan Project to build route DT.384B (section from the intersection with the road connecting the two expressways Hanoi - Hai Phong with Cau Gie - Ninh Binh expressway to the intersection with DT 378)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan Project to build route DT.384B (section from the intersection with the road connecting the two expressways Hanoi - Hai Phong with Cau Gie - Ninh Binh expressway to the intersection with DT 378)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 20

You did not use the site, Click here to remain logged. Timeout: 60 second