Bidder Selection Plan

contractor selection plan Project: Upgrading and expanding roads in hamlet 6-7, Phu Vinh commune Construction location: Phu Vinh commune, Dong Nai city

  Watching      
Find: 12:49 04/07/2026
Contractor Selection Plan ID
PL2600199078-00
Publishing time
12:48 04/07/2026
Posting Status
Published
Contractor selection plan name
contractor selection plan Project: Upgrading and expanding roads in hamlet 6-7, Phu Vinh commune Construction location: Phu Vinh commune, Dong Nai city
Investment objective
In order to upgrade and expand the road surface, build a drainage system to serve the travel and goods transportation needs of people in the area, link areas in the commune, and aesthetically enhance the central area, contributing to perfecting the traffic network according to planning and local socio-economic development.
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2600042993-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Authority that issues the decision
TRƯỞNG PHÒNG KINH TẾ XÃ PHÚ VINH
Approval date
30/06/2026
Approval ID
Số: 99/QĐ-PKT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 8
1.Package 04 (construction and installation): Construction work
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction
Capital source details
Town budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
2.Bidding package No. 05 (consulting): Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision package 04
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
3.Bidding package No. 06 (consulting): Prepare E-HSMT and evaluate EHSDT for bidding package No. 04
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare E-HSMT and evaluate EHSDT for bidding package No. 04
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
4.Bidding package No. 07 (consulting): E-HSMT appraisal and selection results Select contractor for package number 04
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
EHSMT appraisal and contractor selection results for package No. 04
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
5.Tender package No 08 (Non-consulting): Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
545 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
6.Bidding package No. 09 (consulting): Checking the acceptance work project into use
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Check the acceptance work to put the project into use
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2027
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
7.Bidding package No. 10 (consulting): Survey, establish technical design - Control estimates, measure and adjust changes, prepare land plot and set land acquisition boundary markers
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Survey and establish technical design - Control estimates, measure and adjust fluctuations, prepare land plot and set landmarks land acquisition boundary
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No
8.Tender package No 11 (consulting): Checking, measuring and adjusting fluctuations, preparing land plot and setting land acquisition boundary markers
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Check, measure and correct fluctuations, establish land map and set land acquisition boundary markers
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "contractor selection plan Project: Upgrading and expanding roads in hamlet 6-7, Phu Vinh commune Construction location: Phu Vinh commune, Dong Nai city". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "contractor selection plan Project: Upgrading and expanding roads in hamlet 6-7, Phu Vinh commune Construction location: Phu Vinh commune, Dong Nai city" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 27

You did not use the site, Click here to remain logged. Timeout: 60 second