Bidder Selection Plan

Decision 07/QD-UBND

  Watching  
Project Contractor selection plan Bid award
Find: 10:36 22/04/2025
Contractor Selection Plan ID
PL2500089672-00
Publishing time
10:35 22/04/2025
Posting Status
Published
Contractor selection plan name
Decision 07/QD-UBND
Investment objective
Solidification of level 1 canal type 1 type 1 type III - route M7, Binh Nguyen commune, Kien Xuong district to proactively supply irrigation water for arable land area, ensuring the cultivation of village of Xuan Bang village and Quan Hanh village to improve the environment; Serving agricultural production and contributing to the improved new rural construction of Binh Nguyen commune
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500022089-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
1 Years
Authority that issues the decision
Uỷ ban nhân dân xã Bình Nguyên
Approval date
13/01/2025
Approval ID
Quyết định số 07/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Filter name, Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 3
1.Project management consultancy
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting on project management according to regulations
Capital source details
The central budget capital supports the implementation of the National Program of New Rural Construction in 2025 under Decision No. 3213/QD-UBND dated December 24, 2024 of Kien Xuong District People's Committee (phase 1). Commune budget and other legal capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiến Xương District, Hưng Yên
Implementation location (Before merge)
Thai Binh province
2.Consulting for making technical staff, NVKS, cost estimates for surveys, cost estimates for construction economic reports
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting for making technical staff, NVKS, cost estimates for surveys, cost estimates for construction economic reports
Capital source details
The central budget capital supports the implementation of the National Program of New Rural Construction in 2025 under Decision No. 3213/QD-UBND dated December 24, 2024 of Kien Xuong District People's Committee (phase 1). Commune budget and other legal capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiến Xương District, Hưng Yên
Implementation location (Before merge)
Thai Binh province
3.Bidding package 03: Consulting for rating of NVKS and cost estimates of survey, cost of construction technical report
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting for rating of NVKS and cost estimates for survey, cost of construction construction economic reports
Capital source details
The central budget capital supports the implementation of the National Program of New Rural Construction in 2025 under Decision No. 3213/QD-UBND dated December 24, 2024 of Kien Xuong District People's Committee (phase 1). Commune budget and other legal capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiến Xương District, Hưng Yên
Implementation location (Before merge)
Thai Binh province

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Decision 07/QD-UBND". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Decision 07/QD-UBND" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 4

You did not use the site, Click here to remain logged. Timeout: 60 second