Bidder Selection Plan

Drainage ditch in residential area of ​​Chieng Nang and Chieng Vien hamlets, Giao An commune, Lang Chanh district

  Watching      
Find: 09:49 09/06/2023
Contractor Selection Plan ID
PL2300090954-00
Publishing time
09:46 09/06/2023
Posting Status
Published
Contractor selection plan name
Drainage ditch in residential area of ​​Chieng Nang and Chieng Vien hamlets, Giao An commune, Lang Chanh district
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300025167-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Month
Location
Authority that issues the decision
UBND xã Giao An
Approval date
05/06/2023
Approval ID
72/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Package 02: Construction work (including construction insurance costs)
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 4296/QD-UBND dated December 6, 2022 of the People's Committee of Thanh Hoa province, the budget to support the implementation of the National Target Program for New Rural Development and other lawfully mobilized capital sources
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
2.Package 03: Supervision of construction works
Tender/ Prequalification Notice ID
Contract execution period
3 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 4296/QD-UBND dated December 6, 2022 of the People's Committee of Thanh Hoa province, the budget to support the implementation of the National Target Program for New Rural Development and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Location
3.Package 04: Independent audit
Tender/ Prequalification Notice ID
Contract execution period
1 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 4296/QD-UBND dated December 6, 2022 of the People's Committee of Thanh Hoa province, the budget to support the implementation of the National Target Program for New Rural Development and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
4.Package 05: Project Management
Tender/ Prequalification Notice ID
Contract execution period
5 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 4296/QD-UBND dated December 6, 2022 of the People's Committee of Thanh Hoa province, the budget to support the implementation of the National Target Program for New Rural Development and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location
5.Tender package No 01 : Consulting for E-HSMT preparation and E-HSDT evaluation
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 4296/QD-UBND dated December 6, 2022 of the People's Committee of Thanh Hoa province, the budget to support the implementation of the National Target Program for New Rural Development and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Drainage ditch in residential area of ​​Chieng Nang and Chieng Vien hamlets, Giao An commune, Lang Chanh district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Drainage ditch in residential area of ​​Chieng Nang and Chieng Vien hamlets, Giao An commune, Lang Chanh district" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 7

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8521 Projects are waiting for contractors
  • 141 Tender notices posted in the last 24 hours
  • 159 Contractor selection plan posted in the last 24 hours
  • 23702 Tender notices posted in the past month
  • 37154 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second