Bidder Selection Plan

KHLCNT phase 2 Project DD 220KV LT-CNT

  Watching      
Find: 13:54 24/06/2025
Contractor Selection Plan ID
PL2500159010-00
Publishing time
13:52 24/06/2025
Posting Status
Published
Contractor selection plan name
KHLCNT phase 2 Project DD 220KV LT-CNT
Investment objective
- Exploiting the load of 500 kV Long Thanh TBA; Liberation of Nhon Trach 3 Thermal Power Plant. - Safety supply continuously for the load of Ho Chi Minh City area through TBA 220 kV high -tech. - Enhance reliability, linkage between the electrical system in the region.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500039151-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
2025 Years
Authority that issues the decision
TỔNG CÔNG TY TRUYỀN TẢI ĐIỆN QUỐC GIA
Approval date
24/06/2025
Approval ID
188/QĐ-HĐTV
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Package 8: Line construction (paragraph 4 circuit)
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Line construction and installation (paragraph 4 circuit)
Capital source details
Loan and capital EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2025
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Nhơn Trạch District, Đồng Nai
Implementation location (Before merge)
Tỉnh Đồng Nai
2.Package 9: Supply and transport of galvanized steel columns (paragraph 4 circuit)
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Provide and transport galvanized steel columns (paragraph 4 circuit)
Capital source details
Loan and capital EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2025
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Đồng Nai
3.Package 10: Supply and transport single steel columns (paragraph 4 circuit)
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and transport single steel columns (paragraph 4 circuit)
Capital source details
Loan and capital EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2025
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Đồng Nai
4.Package 11: Supply and, transport wires and lightning protection wires (segment 4 circuit)
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and, transport wires and lightning protection wires (segment 4 circuit)
Capital source details
Loan and capital EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Đồng Nai
5.Package 12: Supply, transport insulation, fiber optic cable and accessories (paragraph 4 circuit)
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply, transport insulation, fiber optic cable and accessories (paragraph 4 circuit)
Capital source details
Loan and capital EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
TP. Hồ Chí Minh

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "KHLCNT phase 2 Project DD 220KV LT-CNT". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "KHLCNT phase 2 Project DD 220KV LT-CNT" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 24

You did not use the site, Click here to remain logged. Timeout: 60 second