Bidder Selection Plan

KHLCNT phase 2 Project Installing the second MBA MBA TBA 500KV Thot Not

  Watching      
Find: 13:54 14/02/2025
Contractor Selection Plan ID
PL2500023336-00
Publishing time
13:53 14/02/2025
Posting Status
Published
Contractor selection plan name
KHLCNT phase 2 Project Installing the second MBA MBA TBA 500KV Thot Not
Investment objective
Ensuring electricity supply to the load and meeting the needs of socio -economic development of the southwestern provinces. Reduce the load for transformer (MBA) 500/220KV at the transformer station (TBA) 500kV O Mon, machine 1 of 500kV jaggery TBA and 220kV lines existing in the region. Relieve the capacity of thermal power plants and renewable energy plants in the area. Contribute to ensuring N-1 criteria, strengthening the stability of the electricity system, improving the reliability, safety of electricity supply for the national electricity system
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500005781-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
2026 Years
Authority that issues the decision
TỔNG CÔNG TY TRUYỀN TẢI ĐIỆN QUỐC GIA
Approval date
11/02/2025
Approval ID
191/QĐ-EVNNPT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Package 3: Providing construction survey consulting services; technical design - construction estimate; construction drawing design; bidding documents
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Provide construction survey consulting services; technical design - construction estimate; construction drawing design; bidding documents
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
February 2025
Type of contract
Package and Fixed Price
Prequalification
No
Implementation location (After merge)
Thốt Nốt District, Cần Thơ
Implementation location (Before merge)
Can Tho city
2.Tender package No 4: Providing consulting services to supervise the survey of technical design phase; Consulting on technical design - construction cost estimates
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Provide consulting and supervision services for surveying technical design phase; Consulting on technical design - construction cost estimates
Capital source details
Loans and capital from EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
February 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thốt Nốt District, Cần Thơ
Implementation location (Before merge)
Can Tho city
3.Package 5: Surveying and setting up landmarks, measuring and drawing cadastral maps and performing compensation and site clearance work
Tender/ Prequalification Notice ID
Contract execution period
450 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Surveying, placing landmarks, measuring and drawing cadastral maps and carrying out compensation and site clearance work
Capital source details
Capital EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2025
Type of contract
Package and Fixed Price
Prequalification
No
Implementation location (After merge)
Thốt Nốt District, Cần Thơ
Implementation location (Before merge)
Can Tho city
4.Package 6: Survey, plan, estimate and supervise the clearance of mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
105 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Survey, plan, estimate and supervise construction of bomb, mine and explosive material clearance
Capital source details
Capital EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
March, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Thốt Nốt District, Cần Thơ
Implementation location (Before merge)
Can Tho city
5.Package 7: Construction of clearing mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of clearing mines and explosives
Capital source details
Capital EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
May, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Can Tho city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "KHLCNT phase 2 Project Installing the second MBA MBA TBA 500KV Thot Not". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "KHLCNT phase 2 Project Installing the second MBA MBA TBA 500KV Thot Not" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 8

You did not use the site, Click here to remain logged. Timeout: 60 second